The invention discloses a bailey truss monitoring and controlling method for
squat silo roof construction, and belongs to the technical field of
squat silo construction, and the method comprises the following steps: selecting a plurality of observation points on a bailey truss, binding a line weight which is 1m away from the ground on an upper chord girder of the bailey truss, arranging a 1.5 m steel
pipe beside the line weight, driving the steel
pipe into the ground by 0.4 m, and pasting 200mm scale paper on the top end; during observation, the right-angle side of the
set square is aligned with the tip of the plummet, the scale paper is marked for reading, and the difference value is recorded as the settlement value. Observation is conducted for the first time before concrete pouring, and observation is conducted once
every hour in the pouring process and within 2 hours after concrete pouring is completed. The maximum settlement value of each position is calculated according to the bailey truss structure, and an early warning value is set. According to the invention, by arranging a plurality of vertical bidirectional observation points and covering a key area, multi-dimensional
data acquisition is realized, vertical settlement and horizontal displacement are monitored in real time, the monitoring precision is improved, and the construction safety is guaranteed.