Manpower resource optimization configuration method of multi-assembly line workshop
A technology for optimizing the allocation of human resources, applied in the field of optimal allocation of human resources in the workshop, can solve problems such as the flexible allocation of human resources that has not been proposed
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
specific example
[0045] Specific example: There are three assembly lines in a workshop, and the skill matrix of the staff in the assembly line of the workshop is as follows:
[0046]
[0047] Step 2: Description of the real-time skills requirement matrix for the workstations in a multi-assembly line workshop
[0048]After the workshop operation plan is issued, the plan dispatcher will subdivide the plan into each assembly line, each assembly line process determines the station, and the skill requirements of each assembly line station employee are as follows:
[0049]
frame
install fan with
Inflow pipe
dry bottle
Check air tightness
with the General Prosecutor
total torque
Cheng test
Water chamber buckle
Water tank leak detection
0.6
0.5
0.5
0.6
0.5
0.5
0.5
0.5
[0050] The matrix is: G=[0.6 0.5 0.5 0.6 0.5 0.5 0.5 0.5...