Lifting device and construction method for replacing rake crane bridge

A construction method and technology of jacking device, applied in the direction of lifting device, lifting frame, etc., can solve the problems of high labor intensity, affecting the production progress, restricting the development of the company, etc.

Inactive Publication Date: 2010-07-14
PANGANG GRP ENG TECH +1
View PDF6 Cites 3 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] As one of the important special equipment for the production of steel rails and steel rolling, the rake crane will directly affect the normal production of the factory. " method to dismantle, and then install according to the "bottom-up" method, the construction period of this kind of construction method is about 40-50 days, the construction period is long, the labor intensity is high, not only affects the production progress, but also seriously restricts the company development of

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Lifting device and construction method for replacing rake crane bridge
  • Lifting device and construction method for replacing rake crane bridge
  • Lifting device and construction method for replacing rake crane bridge

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0021] As mentioned in the background information, at present, in the maintenance or replacement of rake cranes, especially the heavy rake crane bridges such as rake crane trolleys, the first method is to remove the rake from top to bottom. Lift the trolley and its accessories, repair or replace the bridge frame, and then restore the trolley and its accessories from bottom to top. This construction method has a long period of maintenance or replacement, high labor intensity, and great pressure on the production of the factory. .

[0022] In order to solve the above technical problems, such as figure 1 As shown, it is a construction method provided by the present invention that can repair and replace the rake crane bridge frame without disassembling and assembling the rake crane traveling trolley. The construction method is as follows: first use the jacking device located below the rake crane traveling trolley 1 to vertically lift the rake crane traveling trolley 1 away from t...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a construction method for replacing a rake crane bridge, in particular an overhaul construction method suitable for the high and synchronous lifting of equipment with relatively complex structure, large equipment dead weight, large equipment three-dimensional size and relatively high spot elevation such as rake cranes. The construction method for replacing the rake crane bridge comprises the following steps of: using a lifting device positioned below a locked rake crane running bogie to integrally lift the rake crane running bogie away from bogie rails positioned on the rake crane bridge along a vertical direction, removing the rake crane bridge needed to be replaced, lifting and mounting a rake crane bridge for replacement on cart rails and connecting and mountingthe rake crane bridge for replacement in position, and finally returning the rake crane running bogie integrally to the bogie rails of the rake crane bridge after the replacement is completed along the vertical direction by using the lifting device.

Description

technical field [0001] The invention relates to a jacking device for replacing the bridge frame of a rake crane, in particular to a jacking device used in the technical field of metallurgical steel rolling hoisting equipment maintenance for equipment with heavy weight, high elevation and large three-dimensional size. lifting device. [0002] The invention also relates to a construction method for using the jacking device to repair or replace the bridge frame of the rake crane. Background technique [0003] As one of the important special equipment for the production of steel rails and steel rolling, the rake crane will directly affect the normal production of the factory. " method to dismantle, and then install according to the "bottom-up" method, the construction period of this kind of construction method is about 40-50 days, the construction period is long, the labor intensity is high, not only affects the production progress, but also seriously restricts the company dev...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): B66F7/16
Inventor 谢超吴荣善鲁洪刘良宁
Owner PANGANG GRP ENG TECH
Features
  • R&D
  • Intellectual Property
  • Life Sciences
  • Materials
  • Tech Scout
Why Patsnap Eureka
  • Unparalleled Data Quality
  • Higher Quality Content
  • 60% Fewer Hallucinations
Social media
Patsnap Eureka Blog
Learn More