Loose bed and bedrock layer mixed water-intaking and well-forming process for geothermal well

A technology of loose layer and bedrock layer, which is applied in the field of the technology of mixing the loose layer and bedrock layer of geothermal wells to draw water into a well, can solve problems such as rising water temperature, and achieve the effects of increasing water temperature, ensuring water output, and improving maximum efficiency

Active Publication Date: 2011-11-23
河北伟业地热新能源科技有限公司
View PDF3 Cites 28 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

However, for areas with poor geothermal resources and undeveloped bedrock structure, if the conventional well-forming process is followed, it will often appear that: when the pore water in the loose layer is taken as the target production layer...

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Loose bed and bedrock layer mixed water-intaking and well-forming process for geothermal well
  • Loose bed and bedrock layer mixed water-intaking and well-forming process for geothermal well

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0011] Geothermal well loose layer and bedrock layer are combined to take water to form a well. The process steps are: ① Drill the well with mud positive circulation drilling technology to a depth of 5-10 meters below the complete bedrock surface; The downhole wall pipe in the non-loose pore water layer section, and the permeable pipe in the loose pore water layer section of the loose layer. ③Annulus filling means injecting cement slurry into the annulus corresponding to the section below the bedrock surface. The filter material is put into the ring hole corresponding to the water layer, and the clay ball is put into the ring hole corresponding to the non-loose pore water layer section of the loose layer. The circulation drilling process uses a drill bit whose diameter is 5-10mm smaller than the inner diameter of the wellbore pipe to continue drilling in the bedrock layer until the bedrock fissure water layer is reached, and the well can be completed when the water temperature ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a loose bed and bedrock layer mixed water-intaking and well-forming process for a geothermal well, and the process provided by the invention comprises the following steps: 1) using a slurry positive circulation well drilling process to perform well drilling till the depth of 5-10m below a complete bedrock surface; 2) sinking pipes, namely sinking a well wall pipe at the section below the bedrock surface and the section of a non-loose porous water layer of a loose bed and sinking a water-permeable pipe below the section of a loose porous water layer of the loose bed; 3)filling annular holes, namely pouring cement slurry into the annular holes corresponding to the section below the bedrock surface, putting a filter material into the annular holes corresponding to the loose porous water layer and putting clay balls into the annular holes corresponding to the section of the non-loose porous water layer of the loose bed; and 4) further using a drill bit with the diameter being 5-10mm smaller than the inner diameter of the well wall pipe to continue drilling in the bedrock layer through a clear water drilling process or a negative circulation well drilling process till a bedrock fracture water layer after the cement slurry waits on cementing for 72 hours and completing the well when the water temperature achieves the design temperature. The well drilling process for the geothermal well is suitable for developing geothermal resources in regions with poor geothermal resources and non-developed bedrock structures.

Description

technical field [0001] The invention relates to a well drilling technology, in particular to a technology for forming a well by taking water from a loose layer of a geothermal well and a bedrock layer by mixing. Background technique [0002] In areas rich in geothermal resources, when digging geothermal wells, only loose layer pore water or only bedrock layer fissure water, structural water and cave water are taken as the target production layer of the well. However, for areas with poor geothermal resources and undeveloped bedrock structure, if the conventional well-forming process is followed, it will often appear that: when the pore water in the loose layer is taken as the target production layer of the well, the water volume can meet the design requirements, and the water temperature is low; When the fissure water in the rock formation is the target production layer of the well, the water volume is small, but the water temperature has increased. If the water from two pro...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): E21B43/00E21B43/10E21B33/138E21B3/00
Inventor 冯红喜冯永军阴文行
Owner 河北伟业地热新能源科技有限公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products