Self-loading and unloading foldable tower crane
A tower crane, self-loading and unloading technology, applied in cranes and other directions, can solve problems such as inconvenience in erection and dismantling, and achieve the effects of simple structure, delaying construction period and strong adaptability
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
specific Embodiment approach 1
[0007] Specific implementation mode one: combine Figure 1 to Figure 4 Describe this embodiment, a self-loading and unloading foldable tower crane in this embodiment includes a working lifting motor 1, a slewing motor 2, a distribution box 3, a counterweight 4, a jib slanting support pull-down rod 5, and an arm motor 6. Lower support rod 7, bracket for installing counterweight 8, tower crane cab 9, luffing motor 10, upper bracket 11, first jib upper tie rod 12, load wire rope 13, first jib A, lifting The center of gravity of the boom 15, the second jib B, the upper tie rod 16 of the second jib, the third jib C, the hook frame 17, the base and tower combination mechanism E of the tower crane, single-rope double hoist Point horizontal boom retracting and folding mechanism F, single-rope three-section horizontal boom folding buffer self-locking device G, twenty-first pulley 18, twenty-second pulley 20 and hook 19, the basic structure of the tower crane The seat and tower body co...
specific Embodiment approach 2
[0008] Specific implementation mode two: combination Figure 5 to Figure 7 Describe this embodiment, the base and tower combination mechanism E of the tower crane in this embodiment includes a support frame E-1, a sleeve frame E-2, a standard section E-3, a rotating shaft E-4, and a quick-hang erection motor E-5, fixed ear plate E-6, first connecting ear plate E-7, second connecting ear plate E-8, first steel wire rope E-9, second steel wire rope E-10, third steel wire rope E-11, Hanger E-12, Tenth Pulley E-13, Eleventh Pulley E-14, Twelfth Pulley E-15, Thirteenth Pulley E-16, Fourteenth Pulley E-17, Fifteenth Pulley E -18, the sixteenth pulley E-19, the seventeenth pulley E-20, the eighteenth pulley E-21, the nineteenth pulley E-22, the twentieth pulley E-22 and two fixed seats E-24 , the sleeve frame E-2 is rotationally connected with the support frame E-1 through the rotating shaft E-4, the sleeve frame E-2 is set on the outside of the standard section E-3 and the two are ...
specific Embodiment approach 3
[0009] Specific implementation mode three: combination Figure 7 This embodiment will be described. In this embodiment, the eleventh pulley E-14 and the tenth pulley E-13 are arranged perpendicularly, and the tenth pulley E-13 and the twelfth pulley E-15 are arranged in parallel. With such a setting, the guiding effect is good, and the operation of the tower crane can be easily retracted and retracted when it is folded and erected. Other compositions and connections are the same as those in the second embodiment.