An ultra-long steel cage and underground continuous wall technology, applied in sheet pile walls, transportation and packaging, load hoisting components, etc., can solve the problems of complicated hoisting steps, low construction efficiency, hidden safety hazards, etc., and achieve simplified hoisting steps, The effect of low construction cost and safety guarantee
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0028] In order to have a clearer understanding of the technical features, purposes and effects of the present invention, the specific implementation manners of the present invention will now be described in detail with reference to the accompanying drawings.
[0029] like Figure 1-Figure 5 As shown, the overall hoisting device for the ultra-long reinforcement cage of the underground diaphragm wall of the present invention includes a main hoisting device and an auxiliary hoisting device.
[0030] The main hanging device comprises a main suspension hook 1, a main shoulder beam 3, a main pulley 5, a main suspension rope 7, a first suspension point 9, a second suspension point 10 and a third suspension point 13. The main hook 1 is connected with the main shoulder beam 3, the main pulley 5 is installed on the main shoulder beam 3, one end of the main suspension rope 7 is fixed on the first lifting point 9, and the other end bypasses the main pulley 5 and the second lifting point ...