A construction method and tram technology, applied in bridges, bridge parts, bridge construction, etc., can solve problems such as difficulty in achieving the level of track elevation, affecting the beauty of bridge structure, and inability to realize bridge mixed right of way, etc., to achieve high economic efficiency Benefits and social benefits, the effect of saving engineering investment
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0027] Embodiments of the present invention will now be described with reference to the drawings, in which like reference numerals represent like elements.
[0028] refer to figure 1 , the construction method of the tram girder of the present invention comprises the following steps:
[0029] S1, after the construction of the substructure is completed, determine the slotting position on the plate girder main body 10 according to the plane position of the line and determine the size of the notch 11 on the plate girder main body 10 according to the size requirements of the rail support platform 12;
[0030] S2, bind the threaded steel bars, fix the formwork, reserve the space of the notch 11 and pre-embed the track structure connecting steel bars at the slotting position;
[0031] S3. Concrete is poured on the steel bars, templates and track structure connecting steel bars and the prestressed steel tendons are stretched to form the plate girder main body 10. Two pairs of notches...