A construction method of a shield tunnel
A technology of shield tunneling and construction method, which is applied in tunnels, infrastructure engineering, earthwork drilling, etc., can solve the problems of low anti-buoyancy, increased tunnel weight, and high cost, and achieves improved anti-buoyancy capacity, reduced engineering volume, Good anti-floating effect
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Publication Date
- 2018-01-02
Smart Images

Figure 1 
Figure 2 
Figure 3
Abstract
Description
technical field
[0001] The invention relates to the field of shield tunnels, in particular to a construction method of shield tunnels. Background technique
[0002] The anti-floating design of the shield tunnel is an important design part of the shield tunnel, which directly affects the line design and the determination of the construction scale of the tunnel. safety factor requirements. Specifically, the anti-floating design of the shield tunnel needs to meet the anti-floating stability requirements, and the formula is as follows:
[0003]
[0004] In the formula: G k - Anti-buoyancy of the tunnel, which is composed of the anti-buoyancy provided by the tunnel's own weight, ballast or other measures;
[0005] f w - buoyancy value of the tunnel;
[0006] K w ——Safety factor of anti-floating stability, check and calculate according to the most unfavorable situation, take 1.05 when the side friction resistance of the formation is not included; when the side friction re...
Examples
Embodiment
[0046] Example: such as figure 1 As shown, a shield tunnel continuous beam anti-floating structure provided in this embodiment includes several caps 3 arranged at intervals along the longitudinal direction of the shield tunnel 2, and all the caps 3 are arranged laterally on the shield tunnel 2 above, and the transverse centerlines of all the caps 3 are perpendicular to the vertical plane where the central axis of the shield tunnel 2 is; each of the caps 3 is provided with several sets of anti-corrosion Pulling piles 4, the number of groups of uplift piles 4 under the same cap 3 is the total number of shield tunnels 2 plus 1, and all groups of uplift piles 4 under the same cap 3 are respectively arranged in the corresponding The two sides of the shield tunnel 2, and two adjacent shield tunnels 2 share a group of uplift piles 4, the number of uplift piles 4 in each group of uplift piles 4 is at least 1, and each group of uplift piles The uplift piles 4 in 4 are also longitudina...