A kind of underground pipeline branch connection construction method

A construction method and technology for underground pipelines, which are applied in the directions of pipeline laying and maintenance, pipes/pipe joints/pipes, mechanical equipment, etc., which can solve the problems of occupying a large amount of surface sites and traffic roads, destroying the surrounding environment, etc. Protection, low investment cost, small effect on the ground part

Active Publication Date: 2017-05-31
TENGDA CONSTR GROUP CORP
View PDF5 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] The purpose of the present invention is to provide a construction method for branch connection of underground pipelines, so as to solve the problems of occupying a large amount of surface sites and traffic roads and destroying the surrounding environment when carrying out branch connection construction of underground pipelines on the surface in the prior art

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A kind of underground pipeline branch connection construction method
  • A kind of underground pipeline branch connection construction method
  • A kind of underground pipeline branch connection construction method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0038] An underground pipeline branching construction method proposed by the present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments. Advantages and features of the present invention will be apparent from the following description and claims. It should be noted that all the drawings are in a very simplified form and use imprecise scales, and are only used to facilitate and clearly assist the purpose of illustrating the embodiments of the present invention.

[0039] Such as Figure 1-6 As shown, an underground pipeline branch connection construction method is used to connect the underground branch pipe 2 with the main pipe 1, including:

[0040] Step 1: Reinforce the external soil of the main pipe where the branch pipe 2 is connected to the main pipe 1;

[0041] Step 2: Use the pipe jacking construction technology to jack the branch pipes close to the outer wall of the main pipe;

[0042] Step 3: Make...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention provides a branch connection construction method for an underground pipeline to enable an underground branch pipe to be connected with a main pipe. The branch connection construction method comprises the steps that the soil body on the outer portion of the part, where the branch pipe is connected into the main pipe, of the main pipe is strengthened; the branch pipe is ejected into the part close to the outer wall of the main pipe through a pipe ejecting construction technology; a hole is formed in pipe wall of the part, where the branch pipe is connected into, of the main pipe; and the branch pipe and the main pipe are connected. By means of the branch connection construction method, it is achieved that branch connection construction of the pipeline is transferred to an underground part from the ground, original pipeline relocation caused by construction is avoided, the defects that a road and the traffic are occupied by ground construction are overcome, the construction method is reliable and environmentally friendly, and generated public hazards such as vibration, noise and dust are reduced to the maximum.

Description

technical field [0001] The invention relates to the field of urban construction, in particular to an underground pipeline branch connection construction method. Background technique [0002] During the construction of underground pipelines on urban roads, there are connections between branch pipes and main pipes. Usually, the foundation pit is formed by excavating the road surface, and then the branch pipe connection construction is carried out in the foundation pit. With the development of urban construction, underground pipelines form a criss-crossing three-dimensional space arrangement under the road surface. When new underground branch pipes are connected to old main pipes, the traditional method often leads to the relocation of a large number of pipelines and the need to occupy crowded traffic roads. At the same time, the vibration noise and dust generated during construction will pollute the surrounding environment. Contents of the invention [0003] The purpose of...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): F16L1/028
CPCF16L1/028
Inventor 孙九春薛武强王建忠陈银河
Owner TENGDA CONSTR GROUP CORP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products