A construction method and a tubular technology, which is applied in the construction field of the tail water gradient section of the tubular unit of the hydropower station, can solve the problems of many curved surfaces and different cross-sections, etc., and achieve the effects of light weight, convenient material selection, and easy handling.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0057] Such as Figure 1 to Figure 6 A construction method for the tail water transition section of the flow path of the tubular unit of the hydropower station shown includes the following steps:
[0058] Step 1. Prefabrication of the tapered gradient formwork: Firstly, a plurality of arc formworks 1 are fixed on the corresponding arc steel trusses 2 to form a tapered panel support body, and then the tapered panel support bodies are arranged at intervals in sequence On the steel frame 4, the lengths of the plurality of tapered panel supports gradually increase along the extension direction of the steel frame 4, and finally the tapered panels 3 are fixed on the plurality of arc-shaped templates 1, thereby completing the tapered gradient Prefabrication of templates (eg figure 2 and image 3 shown); in this embodiment, the number of the tapered gradient templates is two.
[0059] Step 2. Binding of steel bars in the transition section below the center line 17 of the runner; ...