A Method of Elevation Control in Road Construction
A technology for elevation control and road construction, applied in the engineering field, can solve problems such as low work efficiency and mechanical stagnation, and achieve the effect of less error-prone, fast speed and obvious effect.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0037] The present invention comprises the following steps: 1. determine the embankment width 10m that needs to be filled, and prepare a long rope 2 with a length of (10+0.5) m; , 10.25m respectively mark R0~R4, ②Set two elevation control side piles 3 on both sides of the subgrade, the two elevation control side piles are arranged symmetrically with the center axis of the subgrade as a group; ③according to the double slope value of 2% designed for each layer of subgrade and the subgrade width of 10m, the virtual paving elevation of the subgrade center M of this layer is calculated to be 0.1m; ④Fix the two ends of the long rope to the two elevation control sides On the pile, the long rope is perpendicular to the subgrade profile 6, the height of the long rope 2 from the horizon 1 is (0.1+0.2) m, and the distance between point R on the long rope and the middle point N of the long rope is b, then the distance at point R is The design height of the subgrade surface is c=(b*i%+h); ...
Embodiment 2
[0042]The present invention comprises the following steps: 1. determine the embankment width 16m that needs to be filled, and prepare a long rope 2 with a length of (16+0.4) m; , 8.2m, 10.2m, 12.2m, 14.2m, and 16.2m respectively R0~R8, ②Set two elevation control side piles 3 on both sides of the subgrade, and the two elevation control side piles are centered on the central axis of the subgrade The center line is symmetrically set, and each symmetrically set two elevation control side piles is a group; ③ According to the designed double slope value of each layer of roadbed 2% and the roadbed width of 16m, the virtual paving elevation of the center M of the roadbed of this layer is calculated as 0.32m ; ④ Fix the two ends of the long rope on two elevation control side piles respectively, the long rope is perpendicular to the subgrade profile 6, the height of the long rope 2 from the horizon 1 is (0.32+0.3) m, and the distance between point R on the long rope is set The distance ...
Embodiment 3
[0047] The present invention comprises the following steps: 1. determine the subgrade width 12m that needs to be filled, and prepare a long rope 2 with a length of (12+0.6) m; , 12.3m respectively mark R0~R4, ② Set up two elevation control side piles 3 on both sides of the subgrade, the two elevation control side piles are arranged symmetrically with the central axis of the subgrade as the center line, and each symmetrically arranged two elevation control side piles ③According to the double slope value of 2% designed for each layer of subgrade and the width of the subgrade of 12m, the virtual pavement elevation of the subgrade center M of this layer is calculated as 0.24m; ④Fix the two ends of the long rope to the two elevation control sides On the pile, the long rope is perpendicular to the subgrade profile 6, the height of the long rope 2 from the horizon 1 is (0.24+0.1) m, and the distance between point R on the long rope and the middle point N of the long rope is b, then th...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 


