A method for calculating the maximum power supply capacity of 220kv urban power grid division
A technology with maximum power supply capacity and urban power grid, applied in electrical components, circuit devices, AC network circuits, etc., can solve problems such as transient voltage stability can not be ignored
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0048] The present invention defines the TSC of the current 220kV urban grid partition as: the maximum load that the grid can carry under the conditions of transient voltage stability and static safety constraints after an N-1 fault for a certain output state of a power plant in the partition.
[0049] The whole technical solution is divided into the following 3 steps:
[0050] (1) Establish the TSC objective function of the regional power grid
[0051] Assuming that the TSC of the A partition is calculated, the objective function of the TSC is
[0052]
[0053] where TSC A Indicates the maximum power supply capacity of A partition; i∈A indicates that node i is a node of A partition; P Li is the active load of node i.
[0054] (2) Analysis of TSC calculation constraints
[0055] ①Constraints of power flow equation
[0056] Equality constraints are power flow equation constraints, expressed as follows
[0057]
[0058] Variable description in the formula:
[0059] P ...