A Multi-objective Workpiece Scheduling Algorithm Based on Ant Colony Algorithm

A scheduling method and workpiece technology, applied in the direction of comprehensive factory control, comprehensive factory control, sustainable manufacturing/processing, etc., can solve problems such as insufficient quality, simple model, and limited application scenarios of algorithms

Active Publication Date: 2019-04-30
ANHUI UNIVERSITY
View PDF5 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Although the existing job scheduling algorithms on the market can also find feasible solutions to a certain extent, the corresponding problem models are often relatively simple, so they cannot be fully applied to problems in the actual production environment. The quality of the solution found is not high enough
Due to the many workpiece constraints in the actual calculation, the energy utilization efficiency under the dynamic ladder electricity price is weak, and the existing algorithms are often optimized for a single goal, which is difficult to meet the needs of enterprises for simultaneous optimization of multiple goals

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A Multi-objective Workpiece Scheduling Algorithm Based on Ant Colony Algorithm
  • A Multi-objective Workpiece Scheduling Algorithm Based on Ant Colony Algorithm
  • A Multi-objective Workpiece Scheduling Algorithm Based on Ant Colony Algorithm

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0134] In this embodiment, a workpiece scheduling method based on an ant colony optimization algorithm is applied to a scheduling scheme in which n workpieces are scheduled to be processed in batches on K same batch processing machines under the production conditions of time-of-use electricity price, The scheduling scheme is based on the optimization goal of electricity cost A and delay degree B; the time-of-use electricity price is a step function about time, 0 time is the starting point of high electricity price, and the length of high electricity price period is U H , the electricity price during the high electricity price period is C H , the length of the low electricity price period is U L , the low electricity price is C L , the end moment of each high electricity price period is the start moment of the low electricity price period, and the end moment of each low electricity price period is the start moment of the high electricity price period;

[0135] Record the size...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a workpiece scheduling method based on an ant colony optimization algorithm. The workpiece scheduling method is characterized in that workpieces are effectively selected in the scheduling process through the workpiece characteristics by using a Pareto multi-objective method, and production is performed by preferentially using the low-electricity-price period so that two objectives of optimizing electric power cost A and delay degree B can be realized. A better workpiece scheduling scheme is calculated under the environment of the parallel batch processor of the background of industrial time-of-use electricity price so that the utilization rate of enterprise resources and the energy use efficiency can be maximized, optimization of cost control and the production effect of the enterprise production process can be achieved and the market competitiveness of the enterprise can be enhanced.

Description

technical field [0001] The invention belongs to the field of industrial production scheduling, and is a multi-objective workpiece scheduling algorithm based on an ant colony algorithm. Background technique [0002] In the current market environment, the core competitiveness of manufacturing enterprises is not only simple manufacturing capabilities, but also excellent production scheduling algorithms to rationally utilize resources and equipment and improve the utilization of resources and equipment, so as to reduce costs and increase competition power purpose. Although the existing job scheduling algorithms on the market can also find feasible solutions to a certain extent, the corresponding problem models are often relatively simple, so they cannot be fully applied to problems in the actual production environment. The quality of the solution found is not high enough. Due to the many workpiece constraints in the actual calculation, the energy utilization efficiency under t...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): G05B19/418
CPCY02P80/10Y02P90/02
Inventor 贾兆红汪龙
Owner ANHUI UNIVERSITY
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products