Design method of serious ground subsidence area in high-speed railway tunnel crossing area
A technology of land subsidence and design method, applied in design optimization/simulation, geometric CAD, special data processing applications, etc. Deformation and other problems, to avoid tunnel diseases and intrusion problems
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0043] Below, the present invention is described in detail with reference to accompanying drawing and embodiment:
[0044] Such as Figure 1~8 As shown, a design method for the serious ground subsidence area in the high-speed rail tunnel crossing area includes the following steps:
[0045] (i) Obtain the contour map of the settlement rate along the tunnel and the profile map of the settlement rate over the years
[0046] Collect InSAR data for a certain period of time along the tunnel, use PS-InSAR method to extract deformation information, use ArcGIS filter to process abnormal points, and perform vector splicing to obtain contour maps and longitudinal profiles of settlement rates along the tunnel over the years. Such as figure 1 , figure 2 shown.
[0047] (ii) Obtain the corrected multi-year average sedimentation rate V
[0048] On the basis of step (i), the monitoring data of regional benchmarking points are used for correction, and the land subsidence caused by surrou...