Three-spud-in deepwater-drilling annular pressure management method
A technology of annular pressure and management methods, applied in chemical instruments and methods, earthwork drilling, wellbore/well components, etc., can solve problems affecting the safety of on-site operations, reduce return height, improve operation safety, and facilitate operation Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0025] In order to enable those skilled in the art to better understand the technical solution of the present invention, the present invention will be described in further detail below in conjunction with the accompanying drawings and specific embodiments. And the features in the embodiments can be combined with each other.
[0026] like figure 1 and figure 2 As shown, the embodiment of the present invention provides a three-time deepwater drilling annular pressure management method, including the following steps:
[0027] S1. Surface layer: drill hole 70-80m, run into riser 1 and fix it;
[0028] S2. First drilling: after drilling the wellbore to 600-700m below the mud surface, pull out the drill bit and lower it into the casing 2, then inject cement slurry 3 until the annular space is filled, and the cement slurry returns to the mud surface;
[0029] S3, the second opening time: after drilling the wellbore to 1500-1700m below the mud surface, the drill bit is pulled out ...