Calculation method of maximum temperature tensile stress during the construction period of doorway-shaped lining side wall concrete
A technology of maximum temperature and calculation method, applied in electrical digital data processing, instrumentation, geometric CAD, etc., can solve the problems of inability to calculate temperature stress, difficult temperature crack control target, inability to effectively achieve temperature crack control target, etc.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0081] F2-type 1m-thick lining in the non-pressure section of the flood discharge tunnel in the type III1 surrounding rock area of the gate-shaped section
[0082] The F2 1m-thick lining in the Class III1 surrounding rock area is the structural section with the largest number of door-shaped sections in the unpressured section of the flood discharge tunnel, and it is difficult to control the temperature and prevent cracking.
[0083] Such as Figure 5 As shown, the method for calculating the maximum temperature tensile stress during the construction period of the doorway-shaped lining side wall concrete provided by this embodiment includes the following steps:
[0084] Step 1. Collect the data for temperature control and anti-crack calculation of the concrete structure of the lining side wall:
[0085] Lining side wall design data, lining side wall section, concrete strength grade; environmental data, deformation modulus of surrounding rock under geological conditions, annu...
Embodiment 2
[0099] F4-type lining in the non-pressure section of the flood discharge tunnel in the type IV surrounding rock area of the gate-shaped section
[0100] The basic information is the same as above. In order to reduce the length of the paper, only a brief introduction of the summer temperature control calculation results of the F4-type lining in the surrounding rock area of Category IV is briefly introduced.
[0101] In the design stage, the pouring and construction will begin on August 1 in summer, and the temperature in the cave will be T a is 25°C, pouring at 18°C + cooling with water at 15°C, the calculated σ max = 1.74MPa; less than the axial tensile strength standard value is 2.39MPa, so the design and construction scheme meets the requirements. Construction real-time control stage, pouring construction on August 1 in summer, the temperature inside the cave is T a is 25.99°C, pouring at 18°C + cooling with water at 15°C, the calculated σ max = 3.12MPa. The σ ...