Unlock instant, AI-driven research and patent intelligence for your innovation.

Construction method of steel reinforcement framework cement hanging plate applied to waterproof base surface leveling construction

A steel skeleton and construction method technology, applied in basic structure engineering, excavation, construction, etc., can solve problems such as long maintenance time, long construction period, slow construction progress, etc., to achieve convenient construction, good vertical state, and speed up construction progress effect

Active Publication Date: 2019-08-23
TIANJIN CONSTR ENG CO LTD OF CHINA RAILWAY FIRST GRP CO LTD
View PDF3 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] The above-mentioned existing technical solutions have the following defects: during the construction of the sprayed concrete and waterproof mortar leveling layer, the concrete needs to be maintained, and the long maintenance time results in a long construction period and slow construction progress

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method of steel reinforcement framework cement hanging plate applied to waterproof base surface leveling construction
  • Construction method of steel reinforcement framework cement hanging plate applied to waterproof base surface leveling construction
  • Construction method of steel reinforcement framework cement hanging plate applied to waterproof base surface leveling construction

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0042] The present invention will be described in further detail below in conjunction with the accompanying drawings.

[0043] For the construction method of reinforced concrete hanging slabs applied to the leveling construction of waterproof base surface, refer to figure 1 , including the following steps:

[0044] S1. Stretch the ground on the ground, implant the reference steel bar 5 on the construction side of the enclosure structure 1, make a vertical line 51 on the reference steel bar 5 to keep the ground spring line in the center, set two vertical lines 51, and two vertical lines 51 form a vertical plane.

[0045] refer to figure 1According to the design requirements, the wire is stretched on the ground at a certain distance from the enclosure structure 1, and the reference steel bars 5 are set in two, and the two reference reinforcement bars 5 are driven into the construction side of the enclosure structure 1, and the enclosure structure 1 is shaped steel cement For ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to a construction method of a steel reinforcement framework cement hanging plate applied to waterproof base surface leveling construction. The construction method comprises the following steps: S1, a line is formed on the ground via elasticity; criterion steel bars are implanted on the construction side surface of a space enclosing structure; vertical lines are formed on thecriterion steel bars and are aligned with the formed line on the ground; the two vertical lines are formed and form a vertical plane; S2, sectional construction is performed; multiple horizontal pulling lines are arranged on the vertical plane formed by the two vertical lines on a construction section position and are located on the same vertical plane; the pulling lines are fixedly connected to wall surfaces on two ends of the space enclosing structure; S3, fulcrum ribs which are vertical to the space enclosing structure are implanted on the construction side surfaces of the space enclosing structure; S4, the ends, which are far away from the space enclosing structure, of the fulcrum ribs are fixedly connected to framework ribs; S5, the cement hanging plate is fixedly connected to the framework ribs; and S6, a filler layer is arranged between the space enclosing structure and the cement hanging plate. The construction method has the effect that the construction rate of process can beaccelerated.

Description

technical field [0001] The invention relates to the technical field of leveling the waterproof base surface, in particular to a construction method for reinforcing steel skeleton cement hanging boards used in the leveling construction of the waterproof base surface. Background technique [0002] At present, cement hanging board is a new type of interior and exterior wall decoration material, mainly used for facade decoration and renovation of villas, factories and houses; building roof decoration; interior wall decoration, suspended ceiling, partition wall and parapet wall; indoor and outdoor ground decoration; Lattice fence and various garden architectural shapes and accessories. [0003] The auxiliary enclosure structure of conventional stations adopts steel cement mixing walls, and the side wall waterproof base leveling of the enclosure structure is usually constructed with screen shotcrete and waterproof mortar leveling layer. [0004] The above existing technical solut...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E02D17/04
CPCE02D17/04
Inventor 陈高潮张国良李晨尚杰高正方李泽军
Owner TIANJIN CONSTR ENG CO LTD OF CHINA RAILWAY FIRST GRP CO LTD