A construction method and channel technology, applied in tunnels, earth cube drilling, mining equipment, etc., can solve the problems of large ground subsidence, inability to start subway construction, and inability to construct subway enclosure structures, so as to reduce construction costs and shorten construction periods Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0021] In order to enable those skilled in the art to better understand the present invention, the technical solution of the present invention will be further described below in conjunction with the accompanying drawings and embodiments.
[0022] refer to figure 1 with figure 2 , a construction method for reinforcing underground excavation passages, the following steps are adopted:
[0023] One) at first determine the length of the civil air defense passage 6 that needs to be processed, in the present embodiment, determine the length that the civil air defense passage needs to process in conjunction with the influence range of the civil air defense passage to the underground enclosure structure is the thickness of the underground enclosure structure and each plus on both sides thereof At least 2m.
[0024] Two) in order to block the civil air defense passage treatment section determined in step 1), first the two ends of the civil air defense passage treatment section are bl...