Basement waterproof construction method
A construction method and basement technology, applied in water conservancy projects, artificial islands, underwater structures, etc., can solve problems such as waterproof and civil construction methods are random, and achieve the effect of improving construction quality and controllability, and reducing costs
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0149] figure 1 A schematic diagram of the construction nodes of the basement waterproof construction method according to the present embodiment is shown; figure 2 It shows the overall schematic diagram of the waterproof structure of the basement waterproof construction method according to this embodiment.
[0150] Such as Figure 1 to Figure 2 Shown, this construction method comprises steps:
[0151] (1) Excavate the soil layer 24 according to the design elevation, combined with the on-site enclosure structure. grading treatment to form a basement pit structure;
[0152] (2) Ramping the bottom and side walls of the basement pit structure;
[0153] (3) Carry out the construction treatment of the first concrete cushion layer 1 under the structural layer at the lowest elevation according to the requirements of relevant specifications. at least 150mm);
[0154] (4) Build a permanent wall 2 on the first concrete cushion 1 according to the size requirements of the indoor spa...
Embodiment 2
[0178] image 3 A schematic diagram of the construction nodes of the basement waterproof construction method according to the present embodiment is shown;
[0179] Figure 4 A schematic diagram of the construction nodes of the basement waterproof construction method according to the present embodiment is shown; Figure 5 A schematic diagram of the construction nodes of the basement waterproof construction method according to the present embodiment is shown; Image 6 It shows the overall schematic diagram of the waterproof structure of the basement waterproof construction method according to this embodiment.
[0180] Such as Figure 3 to Figure 6 Shown, this construction method comprises steps:
[0181] (1) Excavate the soil layer 24 according to the design elevation, combined with the on-site enclosure structure. The excavation elevation of the soil layer 24 is combined with the minimum structural elevation requirements and the minimum second-floor structural elevation req...