Method for additionally arranging piles on existing bridge pile foundations
A technology for pile foundations and bridges, which is applied in the field of adding piles to pile foundations, and can solve problems such as failure to meet the bearing requirements of bridges, waste, and insufficient length of bridge pile foundations.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0029] The original design lower part of the completed bridge adopts the double-column pier bored pile foundation, and the length of the pile foundation is 10m. The length of the bridge pile foundation is not enough due to the erosion of the construction access road and the flood in the rainy season. Now piles are added to the original bridge pile foundation.
[0030] Step 1: Remove all the concrete of the original tie beam on the top of the pile, and keep the original tie beam reinforcement without cutting off so as to weld with the vertical reinforcement of the cap.
[0031] Step 2: Cut out the protective layer of steel reinforcement within 1.5m of the original pile top, and remove the 1cm-thick steel protective layer within 0.5m of the bottom of the pier. The ring-shaped groove of the concrete pile or column to ensure the close contact with the steel ferrule and the adhesion of the glue to the concrete.
[0032] Step 3: The inner side of the steel plate, piles, and columns ...