Device and method for breaking pile head of foundation pile
A technology of foundation pile head and pile head, which is applied in sheet pile wall, foundation structure engineering, construction and other directions, can solve the problems of low removal efficiency of cast-in-place pile head and difficulty in transporting large pieces of concrete out of the foundation pit.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0030] In order to simultaneously break the cast-in-situ pile head in multiple directions before the initial setting of the concrete, and facilitate the removal of the broken concrete from the formwork, such as Figure 1 to Figure 3 As shown, the present invention provides a kind of device that breaks foundation pile head, comprises material injection pipe 1, and the top of material injection pipe 1 is connected with feed pipe 2, is provided with handle 3 at the upper end of material injection pipe 1, and spraying material The bottom of pipe 1 is fixedly provided with at least 2 sub-nozzles 5, and all sub-nozzles 5 are arranged at intervals on the circumferential direction of material spray pipe 1; A stirring piece 61 is fixedly installed on the lower bottom surface of the device 6 .
[0031] The work flow of the breaking device provided by the present invention is: before the initial setting of the concrete, the breaking device of the present invention is arranged on the insi...
Embodiment 2
[0038] In order to effectively remove the foundation pile head and reduce the damage to the main reinforcement during the removal process, the present invention provides a method for removing the foundation pile head, combined with the above-mentioned device for removing the foundation pile head, including The following steps:
[0039] (1) Erection of a breaking device, which shall be arranged at the overfilling part of the cast-in-place pile before the initial setting of the concrete;
[0040] (2) cutting the cast-in-situ pile head, and forming a high-speed water flow in the breaking device through the high-pressure device to cut the cutting material, so as to cut the cast-in-place pile head;
[0041] (3) Clean the pile head. After the breaking device completes the cutting, withdraw the breaking device and discharge the waste liquid in the formwork. After the initial setting of the concrete, remove the formwork and rinse the exposed steel bars;
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com