Method and device for determining water utilization rate of data center
A data center and utilization rate technology, which is applied in the field of data processing, can solve the problems of not considering the water usage of the data center and the inability to accurately evaluate the water usage rate of the data center, etc.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0029] The process of determining water usage rates based on site operations.
[0030] see figure 2 , figure 2 It is a schematic flow chart of determining the water usage rate of the data center in Embodiment 1 of the present application. The specific steps are:
[0031] In step 201, the total amount of water used by the operation of the data center and the power consumption of IT equipment within a preset time period are acquired.
[0032] In this step, the total amount of water used for data center operation is obtained, including:
[0033] Obtain the total amount of water used for site operation and the total amount of reused water within the preset time;
[0034] Calculate the difference between the total amount of water used for site operation and the total amount of reused water;
[0035] The difference is taken as the total amount of water used to run the data center.
[0036] When the application obtains the water consumption and the electricity consumption of ...
Embodiment 2
[0052] The process of determining source-based water usage.
[0053] see image 3 , image 3 It is a schematic flow chart of determining the water usage rate of the data center in the second embodiment of the present application. The specific steps are:
[0054] Step 301, acquire the total water consumption and IT equipment power consumption of the data center within a preset time.
[0055] In this step, the total water consumption of the data center within the preset time period is obtained, including:
[0056] Obtain the total amount of water used for energy production, site operation, and reused water within a preset period;
[0057] Calculate the sum of the total amount of water used for energy production and the total amount of water used for site operation;
[0058] calculating the difference between said sum and the total amount of reused water;
[0059] The difference is taken as source-based water usage.
[0060] When the application obtains the water consumption...