Operation ticket early warning system
An early warning system and job ticket technology, applied in the direction of instruments, electronic digital data processing, data processing applications, etc., can solve the problems of increasing work intensity such as process approval, increasing the number of job tickets, and high workload, so as to reduce personnel process approval, The effect of improving timeliness and reducing quantity
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0049] combine figure 1 , a job ticket early warning system, comprising a job data acquisition unit 100, a data segmentation unit 200, a type judgment unit 300, a redundancy reduction early warning unit 400 and an output unit 500, the job data acquisition unit 100 is connected to the data segmentation unit 200, The data segmentation unit 200 is connected to the type judgment unit 300 , the type judgment unit 300 is connected to the redundancy reduction warning unit 400 , and the redundancy reduction warning unit 400 is connected to the output unit 500 .
[0050] The job data acquisition unit 100 includes a job permit system and a manual collection system, and obtains job information contained in a job ticket through the job permit system or the manual collection system.
[0051] The data segmentation unit 200 includes a data professional vocabulary for petrochemical enterprises, and the data segmentation unit 200 performs word segmentation on the job content in the job informa...
Embodiment 2
[0056] combine figure 2 and image 3 , an early warning method for reducing redundant job tickets, comprising the steps of:
[0057] Obtain job data S100, collect and sort out job permit tickets through the job permit system, and obtain the job information contained in the job permit ticket. Job content, job start time, job end time.
[0058] Divide the job data S200, according to the preset professional vocabulary, including job object attribute number tables such as G904, 26B, object tables such as furnaces, pipelines, tanks, and operation action tables such as subsidy, replacement, rust removal, and polishing. The job content is segmented into words and punctuated stop words are removed, such as G90 overhaul, replacement of fire protection facilities; floating plate subsidy, which is divided into "G90 overhaul of fire protection facilities replacement floating plate subsidy".
[0059] Determine the job S300 that has the same job content on the same day except for differ...
Embodiment 3
[0068] combine Figure 4 , to obtain job data, manually collect and organize the job permit tickets, and obtain the job information contained in the job permit tickets. Job start time, job end time.
[0069] Segment the operation data, according to the preset professional vocabulary, including the attribute number table of the operation object such as G101, the object table such as oil pipe, valve, lock, and the operation action table such as subsidy, replacement, rust removal, and polishing, and the operation content Segment word segmentation and remove punctuated stop words, such as G101 Overhaul, replacement of fuel delivery parts; valve lock replacement, segmented into "G101 Overhaul of oil delivery parts, valve lock replacement subsidy".
[0070] Determine the job S300 that has the same job content on the same day except for different job numbers, extract the job object attribute number in the job content that belongs to the professional vocabulary, and at the same time ...