Mounting structure for front-end operation of tower crane big arm
An installation structure and tower crane technology, applied in the direction of cranes, etc., can solve the problems of easy falling off of parts, difficult installation, hidden safety hazards, etc., and achieve the effect of strengthening the fixing strength, easy to realize, and stable.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0027] refer to figure 1 , an installation structure for the front end operation of the tower crane boom provided by the present invention, comprising an adjustable and detachable fixed splint one 1 and an adjustable and detachable fixed splint two 2,
[0028] The long flange 11 provided on one side of the fixed splint 1; a number of bolt holes 14 are opened on the fixed splint 1;
[0029] The short flange 21 provided on one side of the fixing splint 2 2; the fixing splint 2 2 is provided with a number of bolt holes 24;
[0030] The long folded edge 11 is provided with a vertical card slot 13; the card slot 13 is dispersedly provided with a number of limiting holes 12;
[0031] The short fold 21 is provided with a vertical card slot 2 23; the short fold 21 provided with the fixing hole 22 is assembled with the long fold 11 provided with the limiting hole 12;
[0032] The part where the limit hole 12 and the fixing hole 22 overlap is provided with a fixing device.
[0033] T...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 


