A construction method and technology of bridge structure, applied in the direction of bridges, bridge parts, bridge materials, etc., can solve the problems of heavy workload and difficult operation.

Pending Publication Date: 2021-02-05
CHINA RAILWAY MAJOR BRIDGE ENG GRP CO LTD
View PDF5 Cites 2 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] Embodiments of the present invention provide a construction method and bridge structure for cast-in-place wet joints, so as to solve the problems in the related art that the method of casting wet joints by hoisting the bottom form with tie rods is not easy to operate and has a large workload

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Cast-in-place wet joint construction method and bridge structure
  • Cast-in-place wet joint construction method and bridge structure
  • Cast-in-place wet joint construction method and bridge structure

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0023] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments It is a part of embodiments of the present invention, but not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

[0024] The embodiments of the present invention provide a construction method and a bridge structure for cast-in-place wet joints, which can solve the problems in the related art that the method of casting wet joints by hoisting the bottom form with tie rods is not easy to operate and has a large workload.

[0025] see figure 1 As shown, a c...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention relates to a cast-in-place wet joint construction method and a bridge structure. The cast-in-place wet joint construction method comprises the following steps that bridge decks are prefabricated, and wet joint bottom plates are arranged on the two opposite sides of each bridge deck; the bridge decks and steel longitudinal beams are erected as a whole; a gap between every two adjacentbridge decks is filled; and concrete is poured on the wet joint bottom plates to form wet joints. According to the cast-in-place wet joint construction method and the bridge structure, the wet jointbottom plates prepared in advance can serve as the bottom dies of the cast-in-place wet joints, the workload of mounting and dismounting of the wet joint concrete bottom dies is reduced, and thereforeconstruction is convenient, and the workload is small.

Description

technical field [0001] The invention relates to the technical field of bridge engineering construction, in particular to a construction method of a cast-in-place wet joint and a bridge structure. Background technique [0002] With the development of bridge construction in our country, bridge industrial prefabrication and assembly technology has become an effective method to ensure the construction quality of bridge construction and shorten the construction period. [0003] In the related art, the wet joint is a key part of the prefabricated bridge deck, and the usual construction of the wet joint is to use tie rods to hoist the bottom form, and then install the side form to pour concrete to form the wet joint. However, this traditional construction method requires the installation of a bottom form, and the bottom form needs to be removed after the concrete reaches a certain strength. The installation and removal of the bottom form requires a construction platform, which is n...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E01D21/00E01D19/12E01D101/26E01D101/30
CPCE01D19/125E01D21/00E01D2101/26E01D2101/30
Inventor 周琳徐平安潘军胡腾飞余本俊王帝李旭东彭聪诚汪问鼎雷运华倪宇陆胜成王凯鹏任晓明
Owner CHINA RAILWAY MAJOR BRIDGE ENG GRP CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products