Semi-fabricated independent cover arch structure for tunnel zero excavation and tunnel entering and construction method thereof

A semi-assembled and arched structure technology, applied in tunnels, tunnel linings, shaft equipment, etc., to achieve the effect of flexible and convenient layout, good stability and waterproof performance, and convenient hoisting and construction

Active Publication Date: 2021-07-02
ZHEJIANG COMM CONSTR GRP CO LTD
View PDF6 Cites 1 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0007] In view of the above deficiencies, the technical problem to be solved by the present invention is to provide a semi-fabricated independent arch structure and its construction method for tunnel entry with zero excavation, so as to solve the construction problem of rapid tunnel entry, improve construction efficiency, reduce The purpose of production cost and reducing the negative impact on the surrounding environment

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Semi-fabricated independent cover arch structure for tunnel zero excavation and tunnel entering and construction method thereof
  • Semi-fabricated independent cover arch structure for tunnel zero excavation and tunnel entering and construction method thereof
  • Semi-fabricated independent cover arch structure for tunnel zero excavation and tunnel entering and construction method thereof

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0034] The present invention will be further described below in conjunction with the accompanying drawings.

[0035] The semi-fabricated independent arch structure with zero excavation in the tunnel, including the entrance foundation 1, the channel steel frame 2, the arch inner ring 3 and the arch outer ring 4, the channel steel frame 2 is fixedly connected to the entrance foundation 1, and the The arch inner ring 3 is fixedly installed on the channel steel frame 2, and the arch outer ring 4 is cast on the outside of the arch inner ring 3. The arch inner ring 3 includes the base collar 5 and the splicing collar 6, and the base collar 5 is fixed Installed on the hole foundation 1, the channel steel frame 2 is positioned and installed through the foundation collar 5, relying on the channel steel frame 2, the splicing collar 6 is fixedly installed on the foundation collar 5 to form an independent arch inner ring 3 , before construction, each component of the independent arch stru...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a semi-fabricated independent cover arch structure for tunnel zero excavation and tunnel entering and a construction method thereof. The semi-fabricated independent cover arch structure comprises a hole foundation, a channel steel frame, a cover arch inner ring and a cover arch outer ring, the channel steel frame is fixedly connected to the hole foundation, the cover arch inner ring is fixedly installed on the channel steel frame, the cover arch outer ring is arranged on the outer side of the cover arch inner ring in a pouring mode, the cover arch inner ring comprises a foundation sleeve ring and a splicing sleeve ring, the foundation sleeve ring is fixedly installed on the hole foundation, the channel steel frame is positioned and installed through the foundation sleeve ring, and the splicing sleeve ring is fixedly installed on the foundation sleeve ring with the channel steel frame as a support. Before construction, all components of the independent cover arch structure are prefabricated, and the prefabricated inner ring is small in segmented weight and convenient to hoist and construct; the arrangement of pipe shed guide pipes is more flexible and convenient, and the influence of the annular length of inner ring sections on the positions of the pipe shed guide pipes does not need to be considered in the prefabricating process of the inner ring sections; an on-site concrete spraying construction technology is adopted for the cover arch outer ring, and the integrity, stability and waterproof performance of a independent cover arch formed through the construction method are good.

Description

technical field [0001] The invention belongs to the field of tunnel arch construction, and in particular relates to a semi-assembled independent arch structure and a construction method for zero-excavation tunnel entry. Background technique [0002] With the deepening of the theory and practice of "Two Mountains" and the strengthening of the concept of environmental protection, more and more "zero excavation" tunneling techniques are used in the construction of highway tunnels. This process can minimize the destruction of vegetation, meet the construction principle of "early entry and late exit" of the tunnel, and achieve the effect of environmental protection, beauty and safety. However, under the condition of low and gentle slope terrain, especially when the height of the slope toe is lower than the height of the top of the arch, the conventional tunnel construction generally needs to excavate the slope body first to form a certain height of the slope and strengthen it, an...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E21D11/18E21D11/22E21D11/00
CPCE21D11/18E21D11/22E21D11/003Y02E10/20
Inventor 刘伟刘录刚诸葛永强于超贾少伟屠张锋冯鑫李林峰朱昭凯
Owner ZHEJIANG COMM CONSTR GRP CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products