[0037] Please refer to Figure 1 to Figure 8 , an embodiment of the present invention provides a drainage construction method for a basement floor, which may include:
[0038] Step 801, please refer to figure 1 , construct the cushion 100 in the foundation pit.
[0039] Step 802, please refer to figure 1 , construct the basement floor 200 on the cushion layer 100 .
[0040] Step 803, please refer to Figure 2 to Figure 3 , constructing the blind groove 210 downward along the upper surface of the basement floor 200 , the blind groove 210 includes a buried groove 211 in a flat section, and drainage grooves 212 located on inclined sections on both sides of the buried groove 211 . The slope angles of the drainage grooves 212 on both sides may be the same or different. The angles of the slopes of the drainage grooves 212 are the same in order to avoid excessive water accumula...