Large-diameter cast-in-situ bored pile head overall breaking system and construction method

A bored-in-situ pile and large-diameter technology, which is applied to sheet pile walls, infrastructure engineering, construction, etc., can solve the problems of easily damaged longitudinal main bars of bored-in-situ piles, low efficiency of mechanical equipment, and easy damage to longitudinal main bars. It is convenient for the overall separation and removal, the formation range is controllable, and the construction quality and construction efficiency are guaranteed.

Pending Publication Date: 2021-07-09
HENAN HIGHWAY ENG GROUP +1
View PDF0 Cites 4 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

The existing pile head removal method is mainly to manually remove the concrete at the pile head with the help of small mechanical equipment such as jacks. This method has a large workload on site and a slow construction speed. During the pile head concrete removal process, the borehole is easily damaged. The longitudinal main reinforcement of the cast-in-situ pile affects the stress of the structure
[0003] In the existing related construction technology, before the pile foundation concrete is poured, materials such as PVC sleeves are used to wrap the longitudinal main reinforcement at the top of the steel cage to avoid direct contact between the longitudinal main reinforcement at the pile head and the concrete; after the pile foundation concrete is poured, the pile Between the pile head and the pile body, the pile head is separated from the pile body by using a pick, steel wedge, etc., and then the pile head is lifted from the pile body as a whole. This construction method can better solve the problem of the grip between the pile head concrete and the longitudinal main reinforcement. However, when this method separates the pile head from the pile body, the efficiency of using mechanical equipment such as pneumatic picks is still low, and the longitudinal main reinforcement is easy to be damaged during the construction process.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Large-diameter cast-in-situ bored pile head overall breaking system and construction method
  • Large-diameter cast-in-situ bored pile head overall breaking system and construction method
  • Large-diameter cast-in-situ bored pile head overall breaking system and construction method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0058] The following will clearly and completely describe the exemplary schemes of the embodiments of the present invention with reference to the accompanying drawings of the specific embodiments of the present invention. Unless otherwise defined, the technical terms or scientific terms used in the present invention shall have the usual meanings understood by those skilled in the art.

[0059] In the description of the present invention, it should be understood that the expressions "first" and "second" are used to describe each element of the present invention, and do not represent any order, quantity or importance limitation, but are only used to describe One component is distinguished from another.

[0060] It should be noted that when an element is "connected", "coupled" or "connected" to another element, it may mean that it is directly connected, coupled or connected, but it should be understood that there may be Intermediate elements; that is, positional relationships co...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention belongs to the technical field of cast-in-situ pile construction. A large-diameter cast-in-situ bored pile head overall breaking system comprises a pile head separation support, isolation sleeves, a first counter-force frame, a second counter-force frame and a driving part, wherein the first counter-force frame and the second counter-force frame are correspondingly arranged up and down; the multiple isolation sleeves are arranged on the pile head separation support, longitudinal main ribs on the upper portion of a steel reinforcement cage of a cast-in-situ pile are arranged in the isolation sleeves in a matched and penetrating manner, and the pile head separation support and the isolation sleeves are poured on the top of the cast-in-situ pile; and a plurality of first counter-force holes are circumferentially distributed in a pile head of the cast-in-situ pile, a plurality of second counter-force holes are circumferentially distributed in the position, on the lower portion of the pile head separation support, of the cast-in-situ pile, and the first counter-force frame and the second counter-force frame are correspondingly arranged in the first counter-force holes and the second counter-force holes correspondingly. The invention further discloses a large-diameter cast-in-situ bored pile construction method. The large-diameter cast-in-situ bored pile head overall breaking system is reasonable in overall design, the problem existing in breaking of the pile head of the large-diameter cast-in-situ bored pile in the prior art can be solved, the breaking efficiency is improved, and the structural damage to a pile body is reduced.

Description

technical field [0001] The invention belongs to the technical field of cast-in-situ pile construction, and in particular relates to a large-diameter bored cast-in-place pile head integral breaking system and a construction method. Background technique [0002] During the construction of bored piles, in order to ensure the pouring quality of the pile body concrete of the bored piles, the pile body is usually overfilled. After the pile body concrete reaches the design strength, the overfilled pile head part is chiseled off. The existing pile head removal method is mainly to manually remove the concrete at the pile head with the help of small mechanical equipment such as jacks. This method has a large workload on site and a slow construction speed. During the pile head concrete removal process, the borehole is easily damaged. The longitudinal main reinforcement of the cast-in-place pile affects the stress of the structure. [0003] In the existing related construction technolo...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E02D13/00E02D13/04E02D5/34E02D15/04
CPCE02D5/34E02D13/00E02D13/04E02D15/04E02D2250/0023E02D2300/002
Inventor 王春李青刘前进魏道平谢琳孟全周合宽刘莉余其蔚聂静刘静刘能源范广宇崔红祥李清燕刘楠
Owner HENAN HIGHWAY ENG GROUP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products