The present application relates to a construction method for installing a
water diversion port without stopping water on a semicircular steel
plate pressure cofferdam, which includes the following steps: S1, marking: marking the outer wall of the side wall of an existing
water storage building where the
water diversion port needs to be constructed, away from the water-facing surface, and performing
strength testing on the side wall of the existing
water storage building. After the strength reaches a preset value, proceed to step S2; S2, installation of the construction platform; S3, installation; S4,
cutting the
water diversion port: after the installation of the
cofferdam steel plate is completed, the water on the inner side of the
cofferdam steel plate is pumped out, and then the water diversion port is
cut by static
cutting. After the water diversion port is
cut and the concrete waste generated by the construction is cleaned up, the construction platform is slid to the next water diversion port marking point of the
water storage building and steps S3 and S4 are repeated; if there is no water diversion port
cutting, the construction platform is slid to the side of the construction channel to dismantle the construction platform. The present application is relatively convenient for opening a water diversion port on the side wall of an existing water storage building.