technical field
[0001] The invention relates to the technical field of bridge construction, and more specifically relates to a prefabricated small box girder bridge construction technology which is half first and then complete. Background technique
[0002] During the construction of traditional bridges, temporary construction access roads (convenience bridges) or temporary access roads (convenience bridges) are usually erected, especially for bridge renovation projects on existing lines, and temporary access roads (convenience bridges) are built for the convenience of people traveling. For example, during the construction of a bridge across a river, for the construction site where the water depth is shallow, a drainage pipe is buried to build a construction access road; for a deep water depth, a steel trestle bridge is erected as a construction access bridge.
[0003] The two ends of the existing cross-river bridge connect tourist attractions and the city center, and there ...