A kind of deep foundation pit slope protection structure
A technology for slope protection and deep foundation pits, applied in infrastructure engineering, construction, excavation, etc., can solve the problems of reducing the service life of the protective net, time-consuming and laborious, and damage to the protective net, and achieves improved service life, reduced pressure, Avoid inconvenient effects
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0050] see Figures 1 to 6 , the embodiment of the present invention provides a deep foundation pit slope protection structure, the protection structure specifically includes:
[0051] Reinforcement mesh cavity, the lower mesh surface 21 is arranged close to the slope surface of the main body 1 of the foundation pit slope, and the aperture of the upper mesh surface 22 is smaller than the aperture of the upper mesh surface 21 and / or the upper mesh surface 22. The hole density of the holes is smaller than the hole density of the holes on the lower mesh surface 21 .
[0052] Specifically, the number of reinforced mesh cavities is four, which are respectively fixed on the four slope surfaces of the main body 1 of the foundation pit slope; and each reinforced mesh cavity includes: a bucket-shaped frame, and the upper trapezoidal frame of the bucket-shaped frame is fixed with a The upper mesh surface 22 and the lower trapezoidal frame are fixed with the lower mesh surface 21, and t...
Embodiment 2
[0063] see Figure 5 , in order to fix and reliably set the steel mesh cavity on the slope surface of the main body 1 of the slope of the foundation pit, the embodiment of the present invention also sets the following structure:
[0064] Four fixing frames, each fixing frame respectively fixes the corresponding steel mesh cavity on the slope surface of the main body 1 of the slope of the foundation pit; Slope); two transverse rods 34, respectively set on the upper and lower parts of the two base rods 31, and the two base rods 31 and the two transverse rods 34 enclose the space as a trapezoidal structure; four anchor rods 32, respectively set On the upper and lower ends of the two base rods 31; four "U"-shaped frames 33 (to facilitate the independent and reliable fixation of the upper mesh surface 22 and the lower mesh surface 21) are respectively located between the two anchor rods 32 On the base rod 31 and the cross rod 34; the connecting piece is used to fix the four sides ...
Embodiment 3
[0069] see Image 6 , in order to effectively transfer the scattered soil that reaches the top of the foundation pit to the ground to determine the position, the embodiment of the present invention also sets the following structure:
[0070] The side wall 61 of the transfer box 6 away from the main body 1 of the slope of the foundation pit is a slope surface structure (while ensuring that the scattered soil in the receiving container 5 is not spilled, the scattered soil in the transfer box 6 can be quickly and completely poured out. For receiving the scattered soil poured into the receiving container 5; the third motor 7, its rotating shaft is fixed with one side wall of the transfer box 6, and the rotating rod and the connecting block that are rotatably arranged on the other opposite side wall of the transfer box 6 Fixed connection.
[0071] The rods of the two telescopic devices 8 are respectively connected with the fixed part and the connection block of the third motor 7 ....