Construction method suitable for highway-railway dual-purpose cable-stayed suspension cooperative system bridge

A technology of cable-stayed suspension and construction method for highway and railway, which is applied in the direction of bridges, bridge parts, bridge construction, etc., can solve the problems that side spans and main towers cannot be constructed synchronously, and the construction period control is unfavorable, so as to save waiting time, Reduce construction difficulty and ensure safety

Active Publication Date: 2021-11-30
CHINA RAILWAY MAJOR BRIDGE ENG GRP CO LTD
View PDF7 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0009] The embodiment of the present application provides a construction method suitable for a bridge with a cable-stayed suspension cooperation system for highway and railway, so as to solve the problem of erecting side-span beams only after the construction of the main tower is completed in related technologies, and only sequential construction can be used. The side span and the main tower cannot be constructed simultaneously, which is unfavorable for the control of the construction period

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method suitable for highway-railway dual-purpose cable-stayed suspension cooperative system bridge
  • Construction method suitable for highway-railway dual-purpose cable-stayed suspension cooperative system bridge
  • Construction method suitable for highway-railway dual-purpose cable-stayed suspension cooperative system bridge

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0050]In order to make the purposes, technical solutions and advantages of the embodiments of the present application clearer, the technical solutions in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments It is a part of the embodiments of this application, but not all of them. Based on the embodiments in the present application, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present application.

[0051] The embodiment of the present application provides a construction method suitable for a bridge with a dual-purpose cable-stayed suspension cooperation system for highway and railway, which includes the following steps:

[0052] S1: see image 3 As shown, the first side span section 20 is installed on the lower beam 1 of the main ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to a construction method suitable for a highway-railway dual-purpose cable-stayed suspension cooperative system bridge, and relates to the technical field of bridge construction. The construction method comprises the following steps: installing a first side span section on a lower cross beam of a main tower, and synchronously constructing an upper tower column on the lower cross beam of the main tower; hoisting a side span section to be erected and connecting same with the first side span section; jacking the erected side span sections so that the erected side span sections can move towards the side span side by a preset distance; hoisting and pushing are repeated until the first side span section is moved to the side pier, so that erection of the side span beam section is completed; after construction of the upper tower column is completed, hoisting the cable-stayed area beam section, and connecting same with the side span beam section; and erecting a main cable synchronously; hoisting the suspension area beam section and the cross area beam section, and closing the cross area beam section and the cable-stayed area beam section to form the cable-stayed and suspension cooperative system bridge. The erection of the side span beam section and the construction of the main tower can be synchronously carried out, the side span beam section does not need to be constructed after the construction of the main tower is completed, and the construction period of a key line is saved through the synchronous construction of the tower and the beam.

Description

technical field [0001] The application relates to the technical field of bridge construction, and in particular to a construction method suitable for a bridge with a cable-stayed suspension cooperative system for highway and railway. Background technique [0002] With the rapid development of bridge construction, since the cable-stayed-suspension cooperative system bridge has the advantages of high rigidity of cable-stayed bridges and strong spanning capacity of suspension bridges, the main tower is lower than that of cable-stayed bridges with the same span, and the dimensions of main cables and anchors are lower than those of cable-stayed bridges with the same span. Suspension bridges are small, so cable-stayed-suspension cooperative system bridges are the preferred solution for long-span road-rail bridges. [0003] Due to the special structure of the cable-stayed-suspension cooperative system bridge, the upper structure includes not only the anchorage, main cable, suspende...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E01D12/00E01D19/00E01D19/14E01D19/16E01D21/00E01D21/06E01D21/10