Folding-arm ladder for equipotential hot-line work of power transmission line and use method of folding-arm ladder
A technology for live work and power transmission lines, applied in overhead lines/cable equipment, ladders, buildings, etc., can solve problems such as poor stability of flat ladders and no reliable load-bearing hanging points, and achieve the effect of improving adaptability and increasing the scope of application
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0031] In a typical embodiment of the present invention, as Figure 1-Figure 2 As shown, a folding arm ladder for equipotential live work of power transmission lines is proposed, which includes a first ladder body 1, a second ladder body 2 and a rotating connector 3 for connecting the two ladders.
[0032] The first ladder body 1 is arranged vertically, the second ladder body 2 is arranged horizontally, the first ladder body 1 and the second ladder body 2 are arranged at an angle, and the bottom of the first ladder body 1 is adjacent to it through the rotating connecting piece 3 The ends of the second ladder body 2 are connected, so that the first ladder body 1 and the second ladder body 2 can rotate relative to each other, so as to improve the adaptability of the folding arm ladder and adapt to different working scenarios.
[0033] It can be understood that the first ladder body 1 and the second ladder body 2 can be perpendicular to each other at 90°, or other angles. The spe...
Embodiment 2
[0054] In another typical embodiment of the present invention, a method of using a folding arm ladder for equipotential live work on a transmission line is proposed, as follows:
[0055] The use scenarios of the folding arm ladder are divided into general use and special use, mainly for the situation where the equipotential maintenance operation cannot be carried out by installing the flat ladder with the force point on the wire due to the damage of the live part itself or the defective structure. The force point is set on the cross arm and the tower body through the folding arm ladder, so that the force point is not on the wire and the stability can be ensured.
[0056] Specifically, the general usage scenarios are mainly used for equipotential treatment of defects in live parts of linear towers, or for equipotential treatment of defects on drainage lines of tensile towers:
[0057] The upper end of the first ladder body 1 is placed on the cross arm angle iron, and the upper ...