Unlock instant, AI-driven research and patent intelligence for your innovation.

Plate combination structure manufacturing method and pre-fabricated reinforced concrete slab and tensioning device

A reinforced concrete and tensioning device technology, applied in the direction of structural elements, building structures, building components, etc., can solve the problem that the joint filling material or compression is not in place, the calibration is affected, and the prestressed state of the prestressed steel bar ends will change. and other issues to achieve the effect of reducing costs

Inactive Publication Date: 2006-05-24
MAX BOGL BAUUNTERNEHMUNG
View PDF2 Cites 11 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

The disadvantage of using this method is that the prestressed state of the end of the prestressed steel bar will change under certain circumstances due to the occurrence of joint filling material or insufficient compaction.
In addition, using this method may affect the calibration, so that it has to be re-checked
Different temperatures also have a negative effect on the accuracy of precast concrete slabs when tensioning and filling butt joints and when gaps in the grouting compound occur

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Plate combination structure manufacturing method and pre-fabricated reinforced concrete slab and tensioning device
  • Plate combination structure manufacturing method and pre-fabricated reinforced concrete slab and tensioning device
  • Plate combination structure manufacturing method and pre-fabricated reinforced concrete slab and tensioning device

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0030] figure 1 Shown is an isometric view of two prefabricated panels 1 and 2 in which the two parts of the tensioning device 3 are arranged. The prefabricated panels 1 and 2 are each only partially shown. In the prefabricated panels 1 and 2 designed for fastening the running track, often a plurality of tensioning devices 3 are distributed over the width of the prefabricated panels 1 and 2 , usually six in number.

[0031] The tensioning device 3 consists of a connecting sleeve 4 and a tensioning box 5 . The connecting sleeve 4 and the tension box 5 are respectively connected with an anchoring steel bar 6,7. The anchor bars 6 and 7 are anchored in the prefabricated panels 1 and 2 . In the region of its ends, at least one of the anchor bars 6 and 7 is placed in the prefabricated panel elements 1, 2 and is stretchable along its longitudinal axis. Stretching can take place, for example, by enclosing the anchoring bars 6, 7 in a tightened hose, which are protected by the anch...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

A method for manufacturing a panel composite structure using reinforced concrete prefabricated panels (1, 2), especially a method for manufacturing a panel composite structure used as a fixed track for high-speed vehicles, comprising at least two prefabricated panels The anchor bars (6, 7) extending in the longitudinal direction of the pieces (1, 2) and terminating in the end face range, and the joints (8) between the adjacent prefabricated panels (1, 2), wherein the two prefabricated The plates (1, 2) are aligned and fixed to each other. The anchoring reinforcements (6, 7) of adjacent prefabricated panel elements (1, 2) arranged substantially in a straight line are connected to each other, and the joint (8) is poured with a joint compound (12). The ends of the two anchor bars (6, 7) are connected to a tensioning device (3) equipped with wedges (14, 17, 18), and the joint (8) is formed by placing the wedges (14, 17, 18 ) is inserted into the tensioning device (3) to obtain prestress. The object of the invention is also the corresponding prefabricated slabs made of reinforced concrete and the tensioning device for connecting and tensioning the anchor bars on the concrete prefabricated slabs (1, 2).

Description

technical field [0001] The present invention relates to a method for manufacturing a panel combination structure by using reinforced concrete prefabricated panels, and corresponding reinforced concrete prefabricated panels and tensioning devices, the panel composite structure is especially used for fixing high-speed vehicles A method for the panel assembly structure of a running track, comprising at least two anchoring reinforcement bars extending in the longitudinal direction of a prefabricated panel and terminating in the end face range, and joints between adjacent prefabricated panels, wherein two prefabricated panels The pieces are aligned and fixed to each other, the anchor bars of adjacent prefabricated panels arranged substantially in a straight line are connected to each other, and the joints are poured with a joint compound. Background technique [0002] A reinforced concrete prefabricated panel of the same type is known from German patent document DE 197 33 909 A1....

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E01B3/40E04B1/61
CPCE04C5/163E01B1/002E04B1/043E04C5/12
Inventor 迪特尔·赖歇尔斯特凡·博尔格拉尔夫·魏德豪泽乌多·希勒
Owner MAX BOGL BAUUNTERNEHMUNG