Vertical prestressing force opening mud jacking construction method and construction device

A technology of vertical prestressing and construction methods, which is applied in the processing of building materials, construction, building construction, etc., and can solve the problems of uncompacted tops of vertical prestressing tunnels, so as to save grouting pipe materials and construction costs , reduce artificial effects

Inactive Publication Date: 2009-11-04
CHINA CONSTR SEVENTH ENG DIVISION CORP LTD +1
View PDF5 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

③Solve the non-compact defect at the top of the vertical prestressed tunnel

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Vertical prestressing force opening mud jacking construction method and construction device
  • Vertical prestressing force opening mud jacking construction method and construction device
  • Vertical prestressing force opening mud jacking construction method and construction device

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0027] Compared with the traditional technology, the core of the present invention cancels the grouting pipe, and changes the anchor backing plate on the top into an iron casting, and directly sets a grouting hole on the iron casting. The steps of the grouting construction method for vertical prestressed channels of the present invention are as follows: for vertical prestressed pipelines, each channel is subjected to secondary grouting according to the procedure of gravity flow first, then low pressure and finally high pressure, and the grouting from top to bottom is adopted. Direction, specific steps; A. Gravity flow is the first choice for grouting for the first time, the time is 5 minutes, and low pressure control is adopted when the vent hole is vented, the pressure is controlled at 0.1MPa, and the time is controlled at 3 minutes; B. The exhaust pipe is blocked, and the second grouting is started, and the pressure is controlled at 0.3MPa until the slurry is full; C. Finally...

Embodiment 2

[0030] The steps of the grouting construction method for vertical prestressed channels of the present invention are as follows: for vertical prestressed pipelines, each channel is subjected to secondary grouting according to the procedure of gravity flow first, then low pressure and finally high pressure, and the grouting from top to bottom is adopted. Direction, specific steps; A. Gravity flow is the first choice for grouting for the first time, and the time is 5.2 minutes. Low pressure control is adopted when the vent hole is grouted, and the pressure is controlled at 0.12MPa, and the time is controlled at 3.2 minutes; B. The exhaust pipe is blocked, and the second grouting is started, and the pressure is controlled at 0.31MPa until the slurry is full; C. Finally, the exhaust pipe is erected so that its height is higher than that of the bellows.

[0031] The construction equipment of the vertical prestressed channel grouting construction method of the present invention: the c...

Embodiment 3

[0034] The steps of the grouting construction method for vertical prestressed channels of the present invention are as follows: for vertical prestressed pipelines, each channel is subjected to secondary grouting according to the procedure of gravity flow first, then low pressure and finally high pressure, and the grouting from top to bottom is adopted. Direction, specific steps; A. Gravity flow is the first choice for grouting for the first time, and the time is 5.3 minutes. Low pressure control is adopted when the vent hole is pumped out. The pressure is controlled at 0.13MPa, and the time is controlled at 3.3 minutes; B. The exhaust pipe is blocked, and the second grouting is started, and the pressure is controlled at 0.32MPa until the slurry is full; C. Finally, the exhaust pipe is erected so that its height is higher than that of the bellows.

[0035] The construction equipment of the vertical prestressed tunnel grouting construction method of the present invention: the con...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a grouting construction method and construction equipment for vertical prestressed tunnels. The method is as follows: for vertical prestressed pipelines, each tunnel is subjected to secondary grouting according to the procedure of gravity flow first, then low pressure and finally high pressure. The grouting direction is from top to bottom; A. Gravity flow is the first choice for grouting for the first time, and low pressure control is adopted when the vent hole is grouted; B. Block the exhaust pipe and start the second time Press the grout until the grout is full; C. Finally, erect the exhaust pipe so that its height is higher than that of the corrugated pipe. The construction equipment includes an upper anchor pad on which a grouting tunnel is opened. Advantages of the invention: no plugging of grouting holes will occur. The material of the grouting pipe is saved, and resources are saved. Reduce labor and save construction cost. Has a strong practicality. The construction period is shortened. The grout is dense and the effect is good.

Description

technical field [0001] The invention relates to a building construction method and equipment, in particular to a vertical prestressed tunnel grouting construction method and construction equipment. Background technique [0002] At present, the traditional vertical prestressed tunnel grouting technology adopts pre-embedded grouting pipes, and the grouting pipes are buried at the bottom of the tunnel. Traditional technology has the following disadvantages: [0003] ①Because the grouting pipe is pre-buried, concrete construction often leads to blockage of the grouting pipe, which seriously affects the subsequent grouting process. [0004] ②The grouting pipe is pre-buried at the bottom of the tunnel, which increases the material of the grouting pipe and increases the construction cost. [0005] ③The grouting pipe is pre-buried at the bottom of the tunnel. This process increases a lot of labor, prolongs the construction period and increases the construction cost. [0006] ④ Du...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E04G21/00
Inventor 焦安亮吕福杰肖必建胡社新徐发祥黄延铮
Owner CHINA CONSTR SEVENTH ENG DIVISION CORP LTD