Management system and method for temporary ground wire of electric power line or equipment
A technology for temporary grounding wire and power line, which is applied in the field of management system for the use of temporary grounding wire for power lines or equipment, can solve problems such as too simple solutions, and achieve the effect of construction safety assurance
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0040] Such as figure 1 , 3 , 4, and 5, a management system for the use of temporary grounding wires for power lines or equipment, consisting of a microcomputer error prevention system 1, temporary grounding wires 2, grounding piles 3, a grounding wire bank 4 including fixed piles 40, and hanging points 5 . The microcomputer error prevention system 1 has functions of simulating operation sequences and directly or indirectly accessing, identifying or controlling the fixed stake 40, the ground stake 3, the temporary ground wire 2, and the hanging point 5. For the convenience of those skilled in the art to understand, in the present invention, the applicant illustrates in conjunction with prior art, but is not the restriction to described microcomputer error prevention system 1; For example: 1) described microcomputer error prevention system 1 adopts microcomputer error prevention system 1 Error system host (or claim five anti-error host) plus the control mode of computer key, ...
Embodiment 2
[0055] Such as figure 1 , 6 , 7, the difference between this embodiment and embodiment one is:
[0056] In this embodiment, the temporary grounding wire 2 adopts a one-to-one mode, that is, one of the chucks 23 is respectively connected to the hanging point connected to the power line or the three-phase conduction of the equipment, and the three plugs 21 are respectively connected to the The three ground stakes 3 are correspondingly connected; correspondingly, only one plug coupling coil 25 needs to be set on the plug 21, and only one ground stake coupling coil needs to be set in the ground stake hole slot 32 37. Of course, for the sake of production uniformity, it is also possible to set three ground pile coupling coils 37, but actually two of them will be idle.
[0057] In order to judge whether the plug 21 is mated and fastened with the ground stake hole 32 , the present embodiment adopts the following structure. A sleeve-type movable part 321' and a spring 322' are arra...