Fast large-cross-section tunnel construction method adapting to complicated and variable geological conditions

A construction method and technology for geological conditions, applied in tunnels, earthwork drilling, mining equipment, etc., can solve problems affecting construction progress, reducing single excavation span, surrounding rock disturbance, etc., to facilitate medium-sized mechanical construction and shorten closure Time, the effect of speeding up the construction progress

Inactive Publication Date: 2012-01-11
CENT SOUTH UNIV
View PDF4 Cites 31 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

The conversion between the full-section method and the step method is convenient and the construction speed is fast, but the construction safety cannot be guaranteed when encountering weak and broken ground
However, partial construction methods such as CD, CRD, and double-side-wall pilot pit method reduce the large cross-section into small sections, shorten the single excavation span, and are conducive to the stability of tunnel construction. However, these partial construction methods have many construction procedures. The interference between each process is large, the construction speed is slow, and the multiple blasting excavations cause frequent disturbances to the surrounding rock, and there are many temporary supports to be removed, which cannot achieve the purpose of economical and rapid construction; especially when encountering When the geological conditions of the tunnel change, there are problems such as difficulty in switching between construction methods, long construction period, high cost, and poor construction quality.
[0003] Generally speaking, under complex and changeable geological conditions, tunnel construction methods need to be changed frequently, and the existing various sub-construction methods are very troublesome to switch between each other, which seriously affects the construction progress and cannot meet the requirements of rapid tunnel construction.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Fast large-cross-section tunnel construction method adapting to complicated and variable geological conditions
  • Fast large-cross-section tunnel construction method adapting to complicated and variable geological conditions
  • Fast large-cross-section tunnel construction method adapting to complicated and variable geological conditions

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0028] like figure 2 As shown in , when the excavation section of the entire tunnel is in a good rock stratum and is equipped with large-scale mechanical equipment, the entire tunnel shall be excavated at one time without dividing into small excavation sections. At this time, the upper, middle, and lower steps The temporary mid-wall and the temporary inverted arches of each step do not need to be constructed.

Embodiment 2

[0030] like image 3 As shown, when the excavation section of the entire tunnel is in a good rock formation and there are medium-sized mechanical equipment, the step method can be used for construction. The temporary partition walls of the upper, middle and lower steps of the tunnel and the temporary inverted arches of each step Can not be applied, the specific construction process is as follows:

[0031] ① Excavate a step, implement the initial support of a cave body structure, and install lock-foot anchors. The lock-foot anchors are required to be welded to the steel frame with Φ22 steel bars in L shape, 2 for each truss.

[0032] ② Excavate 2 parts, drill and set anchor rods, which require L-shaped welding on the steel frame, and spray concrete to the design thickness.

[0033] ③ Excavate 3 parts, and close the initial support in time.

[0034] In the above construction procedures, if the surrounding rock of the working face is relatively weak, the excavation can be carri...

Embodiment 3

[0036] like Figure 4 As shown, when the upper steps of the tunnel are in poor rock formations and the middle and lower steps are in better rock formations, a temporary partition wall is set during the excavation of the upper steps of the tunnel, that is, the upper steps are divided into two parts by the middle partition wall. , the specific construction process is as follows:

[0037] ① Excavate 1 step and seal the face with primary sprayed concrete. The initial support and temporary support of a cave body structure shall be implemented, and the lock-foot anchor rods shall be installed. The lock-foot anchor rods shall be welded to the steel frame with Φ22 steel bars in L-shape, 2 for each shank.

[0038] ②Follow up two parts of excavation and support, the steps are the same as part one.

[0039] ③ Excavate 3 sections, install steel frames, drill and set anchor rods, and the anchor rods are required to be L-shaped welded on the steel frame. Shotcrete to design thickness.

...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a fast large-cross-section tunnel construction method adapting to complicated and variable geological conditions. Middle walls and steps are combined, whether the arrangement of temporary inverted arches of each steps and middle partition walls of upper, middle and lower steps is needed or not is determined according to actual geological condition change conditions and field monitoring information in the tunnel construction process, when the rock surrounding condition becomes poor in the tunnel construction process, temporary support and protection of each excavated parts are respectively implemented, when the rock surrounding condition becomes good, a plurality of small excavated parts can be combined into a large excavated part until the full cross-section one-step excavation forming method is adopted, and division positions of each excavated parts in the construction process is not changed. The method has the advantages that in the construction, the conversion problem of the construction method does not exist when the geological conditions are changed, the construction speed of large-cross-section tunnels under the complicated and variable geological conditions is greatly accelerated, the construction work period is shortened, and the construction cost can be properly reduced.

Description

technical field [0001] The invention relates to a construction method of a tunnel, in particular to a rapid construction method of a large-section tunnel adapted to complex and changeable geological conditions. Background technique [0002] Since the tunnel is located in the underground rock and soil layer, the stratum conditions it traverses cannot be single, including uneven softness and hardness on the cross section, and continuous changes in stratum conditions along the longitudinal section of the tunnel, especially for large-section tunnels. , the inhomogeneity of the strata it traverses will be more significant. At present, for the construction of large-section tunnels, according to the different geological conditions that the tunnel passes through and the supporting conditions of construction machinery and equipment, the full-section method, step method and partial construction methods (including CD, CRD and double-side wall method) are mainly used at home and abroad....

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E21D9/00E21D9/04
Inventor 彭立敏施成华雷明锋杨伟超安永林
Owner CENT SOUTH UNIV
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products