Construction method for mounting scaffolds by using underground wall body ultralong vertical ribs at one step
A scaffolding and sub-installation technology, which is applied to artificial islands, water conservancy projects, underwater structures, etc., can solve problems such as labor and material costs, and achieve the effects of reducing procedures, improving efficiency, and reducing costs
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0016] The present invention will be described in detail below in conjunction with the accompanying drawings and embodiments.
[0017] The construction method of installing the scaffolding at one time with the ultra-long vertical reinforcement of the underground wall described in this embodiment is carried out according to the following steps:
[0018] 1. See figure 1 , image 3 . After the steel bars of the structural bottom plate are bound, the first stage of the double-row scaffolding is erected according to the design position. The position of the large horizontal bar 2 is 300mm above the upper surface elevation of the structural floor. For example: the thickness of the structural bottom plate is 500mm, and the step distance of the double-row scaffolding is 1500mm, then the height of the short steel pipe riser 1 of the first step of the double-row scaffolding is 500+300+1500+200=2500mm.
[0019] 2. Still refer to figure 1 , image 3 . Set up the second step frame. ...