Method for integral ground manufacture, suspension and construction of large-sized steel trestle conveying system
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- 中煤建安第七工程有限公司
- Publication Date
- 2012-05-02
- Estimated Expiration
- Not applicable · inactive patent
Smart Images

Figure 1 
Figure 2 
Figure 3
Abstract
Description
technical field
[0001] The invention discloses a construction method for integrally manufacturing and hoisting the ground of a large-scale steel trestle conveying system, belonging to the technical field of trestle construction. Background technique
[0002] There are currently two commonly used construction methods for large-scale steel trestle conveying system engineering: one is to make steel trusses on the ground, and after hoisting in place, assemble bolts to connect them to form a steel trestle, and then complete the trestle walkway bottom plate pavement and side slab roof panels at high altitude The other is to make steel trestles on the ground, and complete the composite color steel cladding structure of trestle walkway floor pavement and side plate roof panels at high altitude after the overall hoisting is in place. Both of these two construction technologies have problems such as large amount of work at high altitudes, low construction efficiency, slow construction...