Multi-column construction method for jacking and reflowing pump concrete
A technology for pumping concrete and a construction method, which is applied in construction, building structure, processing of building materials, etc., can solve the problem that the strong power of concrete pump cannot be fully exerted.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0053] Embodiment 1 is the first multi-column pumping concrete jacking and backflow construction method, which is applied to a construction site with two steel pipe columns, and the construction steps are as follows.
[0054] Step 1. Arranging a pumping concrete jacking backflow construction system at the construction site. The pumping concrete jacking backflow construction system includes a concrete delivery pump 4 and a concrete delivery pipeline. The maximum pressure at the outlet of the concrete delivery pump 4 is above 15Mpa , the concrete conveying pipeline includes a conveying pipe riser 1, a conveying pipe main pipe 2 and two conveying pipe branch pipes, the outlet of the concrete conveying pump 4 communicates with the conveying pipe standpipe 1, and the conveying pipe standpipe 1 is in turn It communicates with the main pipe 2 of the conveying pipe, and the main pipe 2 of the conveying pipe communicates with one of the branch pipes of the conveying pipe. The main pipe...
Embodiment 2
[0062] Embodiment 2 is the second multi-column pumping concrete jacking and backflow construction method, which is applied to a construction site with three steel pipe columns, and the construction steps are as follows.
[0063]Step 1. Arranging a pumping concrete jacking backflow construction system at the construction site. The pumping concrete jacking backflow construction system includes a concrete delivery pump 4 and a concrete delivery pipeline. The maximum pressure at the outlet of the concrete delivery pump 4 is above 15Mpa , the concrete conveying pipeline includes a conveying pipe standpipe 1, a conveying pipe main pipe 2 and three conveying pipe branch pipes, the outlet of the concrete conveying pump 4 communicates with the conveying pipe standpipe 1, and the conveying pipe standpipe 1 is connected with the conveying pipe riser The main pipe of the conveying pipe is connected with the main pipe 2, and the main pipe of the conveying pipe 2 is connected with the branch...
Embodiment 3
[0073] Embodiment 3 is the third multi-column pumping concrete jacking and backflow construction method, which is applied to a construction site with four steel pipe columns, and the construction steps are as follows.
[0074] Step 1. Arranging a pumping concrete jacking backflow construction system at the construction site. The pumping concrete jacking backflow construction system includes a concrete delivery pump 4 and a concrete delivery pipeline. The maximum pressure at the outlet of the concrete delivery pump 4 is above 15Mpa , the concrete conveying pipeline includes a conveying pipe riser 1, a conveying pipe main pipe 2 and four conveying pipe branch pipes, the outlet of the concrete conveying pump 4 communicates with the conveying pipe standpipe 1, and the conveying pipe standpipe 1 is in turn It is connected with the main pipe 2 of the conveying pipe, and the main pipe 2 of the conveying pipe is connected with the first branch pipe of the conveying pipe (namely branch ...