A technology for tunnel construction and model testing, which is applied to teaching models, educational tools, instruments, etc., can solve problems such as undiscovered tunnel construction model tests and unseen model tests, and achieve simple, practical, easy-to-operate, and low-cost test devices Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0025] The present invention will be described in detail below in conjunction with specific embodiments. The following examples will help those skilled in the art to further understand the present invention, but do not limit the present invention in any form. It should be noted that those skilled in the art can make several modifications and improvements without departing from the concept of the present invention. These all belong to the protection scope of the present invention.
[0026] This embodiment provides a construction model test of a pipe jacking tunnel based on the displacement control method, with a simulated construction length of 1400 mm, a simulated tunnel design diameter of 141 mm, and a formation loss rate of 5%. The specific steps of this embodiment are as follows:
[0027] (1) According to the formation loss rate used in the model test, the required length and diameter of the tunnel deformation device are calculated, as follows:
[0028] The tunnel deform...