Underwater anchor rod construction method
An anchor rod construction and anchor rod technology is applied in the direction of infrastructure engineering, construction, sheet pile wall, etc.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0025] During the construction of Xinglong Water Conservancy Project, the concrete floor of the diversion channel of the power station was disturbed and damaged, and part of the concrete floor was lifted and damaged. There was a local cavity formed by the loss of fine sand in the lower part of the floor. After underwater repair, it was necessary to arrange anchors on the surface of the diversion channel for reinforcement . Such as figure 1 As shown in , the specific steps of the anchor rod arrangement are as follows:
[0026] 1) Construction platform positioning Set up a water construction platform 1 on the water surface of the point to be constructed for placing the drilling rig and the grouting pump;
[0027] 2) Drilling and setting out Drilling and setting out on the bagged concrete layer above the original concrete floor to determine the position of the drilled holes;
[0028] 3) After the underwater casing installation hole position is staked out, first use the φ90mm ca...
Embodiment 2
[0035] In the middle and lower reaches of the Gudongkou Reservoir Project, the concrete bottom plate of the stilling pool was damaged after long-term erosion. After inspection, it was found that there was a depleted layer between the concrete of the stilling pool bottom plate and the bedrock, and the depleted area needs to be grouted As well as the arrangement of anchor bolts for reinforcement, the entire construction area is located underwater. The specific underwater anchor construction and grouting methods are as follows:
[0036] 1) Construction platform positioning Set up a water construction platform on the water surface of the point to be constructed for placing drilling rigs and grouting pumps;
[0037] 2) Drilling and setting out Drilling and setting out at the damaged concrete position of the bottom plate of the original stilling basin to determine the position of the drilled hole;
[0038] 3) After the underwater casing installation hole is staked out, use the casi...
Embodiment 3
[0045] During the construction of Xinglong Water Conservancy Project, the concrete floor of the diversion channel of the power station was disturbed and damaged, and part of the concrete floor was lifted and damaged. There was a local cavity formed by the loss of fine sand in the lower part of the floor. After underwater repair, it was necessary to arrange anchors on the surface of the diversion channel for reinforcement . Such as figure 1 As shown in , the specific steps of the anchor rod arrangement are as follows:
[0046] 1) Construction platform positioning Set up a water construction platform on the water surface of the point to be constructed for placing drilling rigs and grouting pumps;
[0047] 2) Drilling and setting out Drilling and setting out on the bagged concrete layer above the original concrete floor to determine the position of the drilled holes;
[0048] 3) After the underwater casing installation hole is staked out, the casing is used as the drill pipe fi...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com