A tower climbing machine and super high-rise technology, applied to cranes and other directions, can solve the problems of backward floor slab construction, hoisting supporting steel beams, and many operating procedures, and achieve the effects of improved climbing efficiency, safety assurance, safety and reliability
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
specific Embodiment approach
[0019] A kind of specific embodiment of the climbing method of the climbing tower crane in the super high-rise building of the present invention, comprises the following steps: A, install the 3rd inner climbing support steel beam and the inner climbing frame: a temporary hoisting mechanism is installed on the tower crane tower body, Lift the supporting steel beam vertically in a limited space, and fix the hanging basket on the upper structure of the inner climbing tower crane, so that the operator has a stable operating platform;
[0020] B. Install the hydraulic jacking device: install the inner climbing hydraulic jacking device on the inner climbing frame on the second supporting steel beam;
[0021] C. The balance of the tower crane is divided into the balance of the boom tower crane and the hammer tower crane, specifically:
[0022] The trim method of the boom-type tower crane: adjust the position of the center of gravity so that the center of gravity of the upper part of ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com