Construction method for continuous construction by using shield construction machine and matched station thereof

A construction method and shield machine technology, which can be applied to stations, earthwork drilling, railway car body parts, etc., can solve problems such as difficulty in improving construction progress, great impact on station safety, and poor waterproof performance, so as to solve groundwater problems and reduce The effect of abnormal process and good waterproof performance

Active Publication Date: 2015-01-28
BEIJING RAIL TRANSIT CONSTR MANAGEMENT +1
View PDF5 Cites 13 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0005] 1) For the construction of interval tunnels, the construction speed of the current shield tunneling method can reach more than 8 times that of the shallow buried underground excavation method; however, if combined with the station as a whole, the advantages of fast construction speed It has not been fully reflected. On the contrary, due to the poor flexibility of the shield tunneling method, it often causes delays in the construction period;
[0006] 2) The average single-line advancing mileage (about 3km) of each shield machine is far less than its service life (10km), so the utilization rate of the shield machine is low;
[0007] 3) The average tunneling speed and the maximum tunneling speed of the shield tunneling method are very different. The reason is that in the construction process of the shield tunneling method, in addition to the normal procedures such as shield tunneling, segment assembly, and unearthed transportation, most of the time is shielded. The structure is dismantled, hoisted out, transferred, assembled in the well or turned around, etc., which affects the average tunneling speed of the shield machine.
[0009] However, the above-mentioned shield tunneling construction method only solves the problem that the shield machine can pass through the continuous construction interval of the station, and this method itself also has some disadvantages:
[0012] It can be seen from the above that in the construction method of shield tunneling in the prior art, although the shield tunneling machine is used to form a shield tunnel through excavation, after the shield machine completes the excavation work, a large number of follow-up construction operations are required , the required station platform type can only be formed by expanding and excavating on the basis of the formed shield tunnel, so it is difficult to improve the construction progress, and the project cost is relatively high
In addition, the follow-up construction process is also relatively complicated, which has a great impact on the safety of the station, and even brings greater risks than a single construction station
In addition, since in the above-mentioned shield tunneling construction method, a large number of follow-up construction operations are required after the shield machine completes the excavation work, the waterproof performance of this method is poor, and it is difficult to solve the problem of deep subway construction. groundwater conundrum

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method for continuous construction by using shield construction machine and matched station thereof
  • Construction method for continuous construction by using shield construction machine and matched station thereof
  • Construction method for continuous construction by using shield construction machine and matched station thereof

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0102] Embodiment 1: The construction method of large shield tunneling.

[0103] figure 2 It is a schematic flowchart of a construction method using a shield machine for continuous construction in Embodiment 1 of the present invention. image 3 It is a simple schematic diagram of a construction method using a shield machine for continuous construction in Embodiment 1 of the present invention. In the first embodiment, a large shield machine (that is, a large shield machine) is used, so that it can be formed as Figure 4 Station type shown. Such as figure 2 As shown, the construction method of using a shield machine for continuous construction in Embodiment 1 of the present invention may include the steps as follows:

[0104] Step 201, excavating a first temporary shaft and a second temporary shaft at the beginning and end of the station to be excavated respectively.

[0105] Step 202, excavating a first construction cross passage and a second construction cross passage r...

Embodiment 2

[0120] Embodiment 2: The construction method of small shield tunneling.

[0121] Figure 5 It is a schematic flowchart of a construction method using a shield machine for continuous construction in Embodiment 2 of the present invention. Image 6 It is a simple schematic diagram of a construction method using a shield machine for continuous construction in Embodiment 2 of the present invention. Such as Figure 5 As shown, the construction method using the shield machine for continuous construction in Embodiment 2 of the present invention may include the steps as follows:

[0122] Step 501, respectively excavating a first temporary shaft and a second temporary shaft at the beginning and end of the station to be excavated.

[0123] Step 502, excavating a first construction cross passage and a second construction cross passage respectively at the bottom of the first temporary shaft and the second temporary shaft.

[0124] Wherein, since a small shield machine will be used in t...

Embodiment 3

[0142] Embodiment 3: Another construction method of small shield rotary excavation.

[0143] Figure 8 It is a schematic flowchart of a construction method using a shield machine for continuous construction in Embodiment 3 of the present invention. Figure 9 It is a simple schematic diagram of a construction method using a shield machine for continuous construction in Embodiment 3 of the present invention. Such as Figure 8 As shown, the construction method using a shield machine for continuous construction in Embodiment 3 of the present invention may include the following steps:

[0144] Step 801, excavating a first temporary shaft and a second temporary shaft at the beginning and end of the station to be excavated respectively.

[0145] Step 802, excavating a first construction cross passage and a second construction cross passage respectively at the bottom of the first temporary shaft and the second temporary shaft.

[0146] Wherein, since a small shield machine will be...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a construction method for continuous construction to construct subway stations by using a shield construction machine and a matched station thereof. The construction method comprises the following steps: construction cross passages for travelling and turning back of the shield construction machine are respectively formed in the two ends of a station to be excavated; after completing the construction operation of a shield tunnel respectively taking the two construction cross passages as a starting point and a terminal point, the shield construction machine moves to one end of the next shield tunnel to be constructed through the construction cross passage of the terminal point of the shield tunnel and turns back, and continues to excavate the next shield tunnel to be constructed until all shield tunnels of the station to be excavated are formed. The method can greatly reduce the abnormal working procedures of the shield construction machine, accelerate the construction progress, reduce project cost and enrich the station type model of the existing subway stations, and partly solves the problem of groundwater of deep subway construction.

Description

technical field [0001] The invention relates to the technical field of underground engineering, in particular to a construction method for continuous construction using a shield machine and a supporting station thereof. Background technique [0002] At present, the most commonly used construction methods in subway projects generally include open-cut method, shallow-buried underground method and shield tunneling method. However, with the gradual densification of the subway network in various cities in China, the burial depth of the line has further deepened, and many stations and sections have partially entered the confined water formation. Therefore, the traditional shallow burial and underground excavation method, which uses precipitation construction as an auxiliary construction method and requires no water on the face of the tunnel, has been greatly restricted. On the other hand, groundwater resources are increasingly protected, and macroeconomic policies do not allow la...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E21D9/06B61B1/00
CPCB61B1/00E21D9/06
Inventor 郝志宏罗富荣金淮王全贤冯爱军张艳英张建海何海健李松梅王毅杜玉峰赵凯
Owner BEIJING RAIL TRANSIT CONSTR MANAGEMENT
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products