Control technology of elastic hybrid lightweight ballast bed for subway shock absorption and vibration isolation
An elastic and subway technology, applied in the direction of tracks, roads, ballast layers, etc., can solve the problems of difficult control of accumulated deformation of surrounding soft soil, difficulty in achieving shock absorption and vibration isolation effects, long subway lines, etc.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0029] 1. Determine the volume ratio of concrete and EPS particles in the mixed elastic lightweight ballast material according to the design requirements of road shock absorption and vibration isolation. The volume ratio of concrete and EPS particles is 3:2. The higher the design requirements for shock absorption and vibration isolation, the EPS The greater the particle content. Concrete is proportioned according to the requirements of C35, and the density of EPS particles is 12-15kg / m 3 , the particle size of EPS particles is 1-2mm;
[0030] 2. Mix the concrete and EPS particles according to the determined volume ratio, and use a vibrator or a vibrating rod to fully mix the concrete and EPS particles evenly; in order to prevent the vibration during the pouring of the elastic lightweight concrete layer 1 from causing EPS Particles float up and affect the strength and durability of elastic lightweight concrete 1. It is necessary to add polyacrylamide to elastic lightweight con...
Embodiment 2
[0033] 1. Determine the volume ratio of concrete and EPS particles in the mixed elastic lightweight ballast material according to the design requirements of road shock absorption and vibration isolation. The volume ratio of concrete and EPS particles is 3:1. The higher the design requirements for shock absorption and vibration isolation, the EPS The greater the particle content. Concrete is proportioned according to the requirements of C35, and the density of EPS particles is 12-15kg / m 3 , the particle size of EPS particles is 1-2mm;
[0034] 2. Mix the concrete and EPS particles according to the determined volume ratio, and use a vibrator or a vibrating rod to fully mix the concrete and EPS particles evenly; in order to prevent the vibration during the pouring of the elastic lightweight concrete layer 1 from causing EPS The particles float up, affecting the strength and durability of the elastic lightweight concrete 1, and it is necessary to add polyacrylamide to the elastic...
Embodiment 3
[0037] 1. Determine the volume ratio of concrete and EPS particles in the mixed elastic lightweight ballast material according to the design requirements of road shock absorption and vibration isolation. The volume ratio of concrete and EPS particles is 3:1. The higher the design requirements for shock absorption and vibration isolation, the EPS The greater the particle content. Concrete is proportioned according to the requirements of C35, and the density of EPS particles is 12-15kg / m 3 , the particle size of EPS particles is 1-2mm;
[0038] 2. Mix the concrete and EPS particles according to the determined volume ratio, and use a vibrator or a vibrating rod to fully mix the concrete and EPS particles evenly; in order to prevent the vibration during the pouring of the elastic lightweight concrete layer 1 from causing EPS The particles float up, affecting the strength and durability of the elastic lightweight concrete 1, and it is necessary to add polyacrylamide to the elastic...
PUM
| Property | Measurement | Unit |
|---|---|---|
| density | aaaaa | aaaaa |
| particle diameter | aaaaa | aaaaa |
| thickness | aaaaa | aaaaa |