Tie bolt leakage-proof plugging process for frame column formwork
A technology for tie bolts and anti-leakage slurry, which is applied in the fields of formwork/formwork/work frame, on-site preparation of building components, construction, etc., which can solve the problem of poor appearance quality of secondary finishes and large gaps in the reinforcement of tie bolts. , construction inconvenience and other problems, to achieve the effect of increasing the visual quality, excellent visual quality, and reducing the area of lack of ash
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0021] The present invention will be further described in detail below in conjunction with the accompanying drawings and through specific embodiments. The following embodiments are only descriptive, not restrictive, and cannot limit the protection scope of the present invention.
[0022] A frame column formwork anti-leakage slurry plugging process for pull bolts, the formwork structure is shown in the accompanying drawings and attached figure 1 The direction shown will be explained, and the specific construction process is as follows:
[0023] (1) Install template 2, this embodiment adopts a template with a thickness of 12mm;
[0024] ⑵Install the horizontal back ribs, install a plurality of horizontal back ribs 3 evenly distributed on the formwork, the installation distance is 600mm, the back ribs of this embodiment adopt 50mm*80mm square wood;
[0025] (3) Install the tension bolts, install tension bolts 6 on the formwork between the transverse back ribs, and insert a leak-...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 