Medium and long term power grid planning method for optimizing new energy construction and grid connected time sequence
A power grid planning and new energy technology, applied in instruments, data processing applications, forecasting, etc., can solve problems such as rational dependence and difficulty in obtaining power grid planning solutions
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0050] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.
[0051] A medium and long-term power grid planning method for optimizing new energy construction and grid connection timing, comprising the following steps:
[0052] Step S1: Obtain system operation forecast data: including grid structure data, new energy planning data and new energy consumption level; the system operation forecast data includes load growth forecast data, installed capacity of each power source, and upper and lower limits of unit output value; the grid structure data includes the total number of nodes N of the grid, and at this stage, the new energy sending line set Ω is limited 0 And the transmission power limit value of each line It is allowed to create a new line corridor m, and the line corridor allows the number of new lines n m , the new energy capacity S caused by the new line k k , the transmission power li...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More - R&D
- Intellectual Property
- Life Sciences
- Materials
- Tech Scout
- Unparalleled Data Quality
- Higher Quality Content
- 60% Fewer Hallucinations
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2025 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com