A real-time monitoring system and sewage treatment plant technology, applied in chemical instruments and methods, biological water/sewage treatment, water/sludge/sewage treatment, etc., can solve the problem of aerator maintenance, replacement and shutdown, and failure to warn aerators Cleaning requirements, difficult replacement of aerators, etc.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0077] An AAO process sewage treatment plant uses corundum spherical aeration discs, with a treatment capacity of 100,000 tons per day, divided into two parallel series, with a total of 10 aeration areas. use as figure 1 The measurement and control devices are arranged in the manner shown, and the specific method is: the electromagnetic inflow flowmeter of E+H company is arranged on the two parallel series of water inlet pipelines, and the gas pressure meter of E+H company is arranged on the main aeration pipe. The gas pressure gauge and gas mass flowmeter of E+H Company are respectively arranged on the 10 aeration branch pipes, and the domestic V-shaped ball valve is proportional to adjust the gas flow of the branch pipes. Due to technological reasons, the liquid level gauge in the aeration area is not installed. The system controller adopts the Siemens S7-300 programmable controller, in which the ladder diagram is used to write the program; each measurement control device is...
Embodiment 2
[0087] An underground sewage treatment plant adopts such as figure 1 The measurement and control devices are arranged in the manner shown, specifically, the influent liquid flowmeter, the gas pressure gauge of the aeration main pipe, the gas pressure gauge of the aeration branch pipe, the air flow equal ratio regulating valve (rhombic valve) of the aeration branch pipe, etc. are installed, and the aeration pipe is not installed. Liquid level gauge in gas zone, gas mass flowmeter in branch pipe.
[0088] In the same manner as in Example 1, according to the real-time monitored aeration area inflow flow Q in Use formula (1) to estimate and calculate the water depth value H of the aeration area L .
[0089] Since the gas mass flowmeter in the branch pipe is not installed, it is necessary to monitor the real-time gas pressure P of the main pipe 0 The valve opening D of the equal ratio regulating valve with the branch pipe flow and the branch pipe gas pressure value P 1 , accord...