A simulation test method for quick-disconnection setting of high-voltage power grid in mixed structure mine
An inspection method and technology for high-voltage power grids, applied in the direction of measuring electricity, measuring devices, measuring electrical variables, etc., can solve problems such as skipping trips
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0057] attached figure 1 And attached figure 2 The branch nodes filled in black are in the open state, and the unfilled branch nodes are in the closed state; figure 1 And attached figure 2 In the mine high-voltage power supply system, the power supply branch nodes are (1), (2), (3) and (4).
[0058] against attached figure 1 The mine high-voltage power supply system generates correlation matrix A, correlation matrix B, correlation matrix D, correlation matrix E and correlation matrix TE; the specific steps are as follows:
[0059] (1) Generate an incidence matrix A, ;
[0060] (2) Generate an incidence matrix B, ;
[0061] (3) Generate an incidence matrix D, ;
[0062] (4) Generate an incidence matrix E, ;
[0063] (5) Generate an incidence matrix TE, .
[0064] Calculate the final power supply correlation matrix of the main road node and the branch road node according to the correlation matrix A and B , the specific calculation steps are as follows:
[...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 