A simultaneous construction method of filling enclosure for dredging filling construction
A technology of dredging filling construction and construction method, which is applied in the fields of soil protection, infrastructure engineering, construction, etc., and can solve problems such as increasing construction costs and affecting construction progress, so as to improve construction efficiency, reduce engineering costs, and make full use of the site resource effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0025] The specific embodiments of the present invention will be further described in detail below.
[0026] A simultaneous filling and enclosure construction method for dredging filling construction, characterized in that: the method includes the following steps:
[0027] (1) Preparation for starting work:
[0028] Carry out water depth measurement in the construction area to determine the position of the cutter suction vessel;
[0029] On-site drilling and sampling of the geology to determine the soil quality;
[0030] According to the soil conditions, determine the slope ratio of the cutter-suction ship to blow and fill the beach, combine the height of the blow-fill and the boundary range of the land area, calculate the location of the cofferdam, and determine the number and location of the pipeline layout; according to different soil conditions The class sets the slope ratio of the blow-fill beach, as shown in the following table:
[0031] Soil slope ratio ...